Construction Safety Inspection Checklist

Construction Safety Inspection Checklist

Checklist.doc Page 1 of 5
Construction Safety Inspection Checklist
Instruction: Place next to each item that is satisfactory. Place Xnext to items with deficiencies. Mark deficiencies in COMMENTS section. Once
corrected, record Corrective Action and Date next to item. If item is not applicable, place NA.
NOTE: This checklist is to identifyminimumsafety & health conditions and should not limit awareness to other safety and health hazards at the jobsite.
Site (Trailer) Facility Security and Public Safety
Safety Representative
Site Perimeter Fence
Emergency Phone Numbers Posted
Warning Signs (hard hats, No Trespassing, etc.)
First Aid Supplies Accessible
Travel/Access ways (unobstructed and maintained)
First Aid Supplies Stocked
Adequate Lighting for Site and Public
Eye Wash Available and Maintained
Necessary Detours, Canopies, Sidewalks
Blood borne Pathogen Kit
Traffic Control Plan / Necessary Traffic Details
Fire Extinguisher
Holes - protected by barriers/barricades/ MARKED covers
Posters (OSHA, etc)
Guardrails > 6 feet high
Copy of Company Safety & Health Program & MSDSs
Visitor Controls (Signs, Visitor PPE, etc)
Training Records including Tool Box Safety Meeting Records
PPE Housekeeping
Hard Hats AT ALL TIMES
Exits and Access ways :Maintained / Unobstructed
Safety Glasses (goggles for liquids)
Trash Receptacles: Adequate Number / Maintained
Hand Protection
Materials Storage
Foot Protection
Projecting Nails
Hearing Protection
Trash Piles
Protective Coveralls/Aprons (Chemical or Flame Resistant)
Enclosed Trash Chutes (> 20 feet high)
Traffic Vests / Traffic Paddles
Toilet Facilities (adequate number)
U.S. Coast Guard Approved Life Jackets (work over water)
Contractors' Responsibilities
Some occupations (not a complete list) for which foot protection should be routinely considered are: carpenters, electricians, mechanics
and repairers, plumbers and pipe fitters, structural metal workers, drywall installers and lathers, sawyers, welders, and laborers.
Checklist.doc Page 2 of 5
Fire Protection / Prevention Contractor (Subs) Provisions
Fire Prevention Plan / Evacuation Plan
(Communicated to All)
Ensure All Contractors Have Site Specific Safety Plan Or
GC's is Followed
Fire Extinguishers (Adequate Number, Type & Maintained)
All Contractor's Have Designated Safety Rep/Competent
Person
Gas Cylinders (Storage/ Proper Separation & Use)
All Contractors Have Submitted HazComm Program and
MSDSs
Hot Work - Adequate Fire Watch (torches & welding)
All Contractors Are Conducting Safety Orientation w/new
Employees
Smoking Policies
All Contractors Holding Tool Box Safety Meetings
(maintaining records
Fire Hydrants /Standpipes (accessible to Fire Dept)
All Contractors are familiar with Emergency Action Plan
Necessary Permits Obtained from Fire Department
Fall Protection Scaffolding
Guardrails (42" Top/21" Mid/4" toe; 200# capacity; 3"rail
deflection
Competent Person Designated (Erect, Use, Dismantle)
Holes/Openings Covered or Barricaded (capacity 2x Intended
load, secure, marked Ahole@or ACover@)
Anchored to Structure
Nets
Proper Access (NO CLIMBING CROSS BRACING)
Positioning Devices
Cross Bracing AND Level / Plumb
Personal Fall Arrest Systems (Full Body Harness, Shock
Absorbing Lanyard, Double Locking Snap Hooks, 5000#
Capacity Anchorage Point
Overhead Protection (access under deck barricaded,
extended toe boards, mesh)
Leading Edge (200 # Warning Line, Safety Monitor,
Employee Training)
Erection & Dismantling (fall protection and proper
procedures)
Residential Roofing (Fall Protection Plan, Slide Guards,
Training)
Guardrails (Top & Mid Rails, Toe Boards)
Independent Lifeline for Suspended Scaffolds
Falling Object Protection (Hard Hats, Canopies, Debris Nets)
Employee Training
Employee Training/Certification
All Pins in Place (coupling pins)
Contractor Fall Protection Plan (on file at site)
100% Fall Protection Rule
Base Plates & Mud Sills
Checklist.doc Page 3 of 5
Electrical Hand & Power Tools
Power Tools (Good Condition, Removed From Service if
Defective)
Tools Inspected Frequently (at least before each use)
Cords & Plugs (3 Prong, Heavy Duty, Not Damaged)
Tools effectively grounded or Double Insulated
All Electrical Receptacles GFCI Protected
Tools Used Properly
Breakers Labeled, High Voltage Signs Posted and Adequate
Access
Damaged Tools Tagged & Removed from Service
Temporary Lighting (Adequate Bulb Guards, Suited for
Location, No Empty Sockets, Not Used as Power Drop)
Hoses Inspected Frequently for deterioration or damage;
Whipchecks/Safety Pins in Place
Installations are Appropriate for Location (weather, flammable)
Proper PPE Worn
Lockout/Tagout Program in Place
Tools Equipped with Required Guards
Extension Cords with Grounding Conductor
Tools Properly Stored
Flexible Cords and cables with No Splices or Taps
Cutoffs/Kill Switches/ Anti-Restart Functioning
Location of power lines identified prior to digging, drilling, etc
Exposed Live Parts (ex knockouts) Covered/Closed
Cranes / Hoists / Elevators Heavy Equipment
Licensed/Qualified Operator (On File At Site)
Licensed/Qualified Operator (On File At Site)
Annual Inspection
Inspections/Service Records/Operators Manual (Filed At
Site)
Daily Inspections (Reports on File & Up to Date)
Seat Belts (Function Properly, Being Worn)
Load Charts Available on Crane
Defective Equipment Removed from Service and Corrected
Outriggers Fully Deployed or Using AOn Rubber@ Chart
Horns/Back Up Alarms (Heard Above Surrounding Noise)
Floats/Tracks on Mats or Pads
Roll Over Protective Structures (ROPS)
Swing Radius Protection
Falling Object Protective Structures (FOPS)
Minimum 10' Clearance from Overhead Power Lines
Prohibition of Unauthorized Riding on Equipment
Hooks/Rigging
Fly Wheel, Belts, Gears, Rollers, Other Pinch Points
Guarded
Pick Plan reviewed for Major Lifts
Swing Radius Protection
Hoist Certified and Inspected
Proper Clearance From Edges of Drop-offs / Unstable
Surfaces
Checklist.doc Page 4 of 5
Hoist Capacity Clearly Posted
Proper Clearance From Powered Utility Lines (> 10 feet)
Hoist Communication System
Security (Protected From Vandalism, Keys Removed
Nightly)
Employees Kept Clear of Suspended Loads
Trenching & Excavations Ladders / Stairways
Inspected Daily (only heavy duty ladders used)
Damaged Ladders removed from service immediately
Anchored / Tied Off and Extend 3 feet above Landing
1 : 4 Pitch
Training and Insurance of Proper Use
Stair Rails ( 4 or more risers, withstand 200 lb load )
Proper Pitch ( Betw 30 & 50 Degrees from Parallel )
Risers - Uniform Height and Width
Landings (not less than 30" in travel direction every 12 vert. ft)
Steel Erection Concrete & Masonry
Fall Protection (including 100% above 6 feet)
Formwork Shoring and Bracing
Access/Egress to Work Locations
Access to Pour Areas and Proper Access Up Shoring
Bolt-Up Procedures Being Followed
Curing/Form Stripping Procedures (In Place & Followed)
Welding/Hot Work
Rebar Protected/Covered
Connecting From Ladders / Aerial Lifts Use Where Possible
Tools/Equipment Inspected Before Use (Concrete
Bucket/Rigging, Floats, Vibrators, Electric Cords, Whirly Birds,
Masonry Saws, Etc.
Rigging/Tag Lines
Proper PPE used
Decking Operations
Scaffolding
Overhead Protection
Brick/Block Walls Properly Supported (Where Applicable)
Checklist.doc Page 5 of 5
Welding & Cutting Demolition & Blasting
Performed by Qualified Individuals
Demolition Plan in Place (On File at Site)
Proper Work Area (All Fire Hazards Removed or Properly
Utilities Disconnected, Purged, Etc.
Fire Watch Posted
HazMat Remediation Activities
Proper PPE Used
Access/Egress
Equipment Inspected Before Use
Chutes/Holes (Properly Constructed & Barricaded)
Hoses & Welding Leads in Good Repair
Hot Work/Fire Protection
Torch Regulators & Gauges in Good Repair
Blasting Plan in Place (On File at Site)
Torches with Flash Arrestors or Check Valves
Licensed Blaster Present at All Times
Fuel Gas Shut Off Key/Wrench Available
All State & Local Permits on File
Cylinders Upright and Secured
Storage Facilities/Usage Logs
Separation of stored Oxy & Fuel Gases/oils by 20' or 1/2 hr
fire-rated wall
Use, Handling & Disposal of Blasting Materials / Packages
Fully Charged Fire Extinguisher Available
Blast Mats
Post Blast Inspection Procedure/Misfires
Warning System/ Warning Signs
Hazardous Substances Traffic Control
Abatement Plan in Place (On File at Site)
Traffic Control Plan (Approved by Jurisdiction & On File at Site
Contractor Competent Person
Traffic Control Manager/Competent Person
Industrial Hygienist/Air Monitoring/Testing
Manager/Traffic Control Personnel Certified by Jurisdiction (if required)
Employee Training/Certifications (Records Maintained
on Site
Flaggers (Trained, Reflectorized Vests, Stop/Slow Paddles, Boots,
Hardhat)
Containment Systems
Barricades/Delineators/Signage (Installed Per Approved Plan)
Storage/Disposal
Dumpsters, Trailers, Etc., Parked on Public Road W/O Permit
Other
Other
Comments:
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
Site Safety Rep Signature______________________________________________________
Login to HandyPDF
Tips: Editig or filling the file you need via PC is much more easier!
By logging in, you indicate that you have read and agree our Terms and Privacy Policy.