Job = 624 - JOHN Q SAMPLE ADDITION, Phase = 0 - None
08/17/09
Gantt Chart
S
12 Oct 08
MT WT F S S
19 Oct 08
MT WT F S S
26 Oct 08
MT WT F S S
2 Nov 08
MT WT F S S
9 Nov 08
MT WT F S S
16 Nov 08
MT W
2 PERMITS
PERMITS
2.3 PLUMBING PERMIT
PLUMBING PERMIT
2.4 ELECTRICAL PERMIT
ELECTRICAL PERMIT
2.5 HVAC PERMIT
HVAC PERMIT
4 SITE PROTECT'N
SITE PROTECT'N
10 *DEMOLITION
*DEMOLITION
53 *CONCR. FOOTING
*CONCR. FOOTING
60 *EXTERIOR STAIR
*EXTERIOR STAIR
68 CHIMNEYS
CHIMNEYS
74 **STRUCT. STEEL
**STRUCT. STEEL
75 **ROUGH CARPT'Y
**ROUGH CARPT'Y
76 **EXTERIOR TRIM
77.2 ORDER DOORS/GLAZING
ORDER DOORS/GLAZING
77.3 DELIVER DOORS/GLAZING
DELIVER DOORS/GLAZING
77.4 INSTALL DOORS/WINDOWS
79 **GARAGE DOORS
79.1 **OD GARAGE DOORS
**OD GARAGE DOORS
85 **ROOFING
**ROOFING
86 *GUTTERS,SPOUTS
90 *SIDING
92 *BRICKWORK
97.1 HVAC SELECTION
HVAC SELECTION
97.2 HVAC ROUGH IN
97.3 HVAC FINISH
98.2 PLUMBING ROUGH IN
98.4 PLUMBING FINISH
99.01 OD DECO ELECTRICAL FIXT
99.1 OD ELECTRICAL PLAN
99.2 ELECTRICAL ROUGH IN
99.4 ELECTRICAL FINISH
75.4 ROUGH INSPECTION
98.3 PLUMBING INSPECTION
99.3 ELECTRICAL INSPECTION
102.1 OD SPEAKERS
102.2 SPEAKER ROUGH
102.3 SPEAKER FINISH
110 OD PLUMBING FIXTURES
OD PLUMBING FIXTURES
110.1 ORDER PLUMBING FIXTURE
ORDER PLUMBING FIXTURES
112.1 OD FINISH HARDWARE
112.3 INSTALL FINISH HARDWAR
120 **INSULATION
120.1 **INSULATION INSPECTION
126 *DRYWALL
136.1 OD TRIM
OD TRIM
136.4 INSTALL TRIM
137 *CASEWORK
138 *STAIRWORK
146 *CLOSET
161.1 OD CABINETS
OD CABINETS
161.2 DELIVER CABINETS
161.3 INSTALL CABINETS
162.1 OD COUNTERTOPS
162.4 *TEMPLATE COUNTERTOPS
162.3 INSTALL COUNTERTOPS
163.1 OD APPLIANCES
163.3 INSTALL APPLIANCES
171.1 OD VANITIES
171.2 DELIVER VANITIES
171.3 INSTALL VANITY
173.1 OD ACCESSORIES
173.3 INSTALL ACCESSORIES
174.1 MIRROR MEASURE
174.2 MIRROR INSTALL
175.2 MEASURE SHOWER DOORS
175.3 INSTALL SHOWER DOORS
181.1 OD CERAMIC TILE
181.2 ORDER CERAMIC TILE
181 CERAMIC TILE
185.1 OD WOOD FLOOR
185.2 INSTALL WOOD FLOOR
189 *CARPET
191.1 OD VINYL FLOOR
191 *VINYL FLOOR
196 *INT. PAINTING
196.1 OD INT PAINT COLORS
197 *EXT PAINTING
197.1 OD EXT PAINT COLORS
T F S S
23 Nov 08
MT WT F S S
30 Nov 08
MT WT F S S
7 Dec 08
MT WT F S S
14 Dec 08
MT WT F S S
21 Dec 08
MT WT F S S
28 Dec 08
MT WT F S S
4 Jan 09
MT WT F S S
11 Jan 09
MT WT F S S
18 Jan 09
M
*DEMOLITION
**STRUCT. STEEL
**EXTERIOR TRIM
INSTALL DOORS/WINDOWS
**GARAGE DOORS
**ROOFING
*GUTTERS,SPOUTS
*SIDING
HVAC ROUGH IN
PLUMBING ROUGH IN
OD DECO ELECTRICAL FIXTURES
OD ELECTRICAL PLAN
ELECTRICAL ROUGH IN
PLUMBING INSPECTION
OD SPEAKERS
SPEAKER ROUGH
OD FINISH HARDWARE
*STAIRWORK
OD COUNTERTOPS
OD APPLIANCES
OD VANITIES
OD ACCESSORIES
OD CERAMIC TILE
ORDER CERAMIC TILE
OD WOOD FLOOR
OD VINYL FLOOR
T
WT F S S
25 Jan 09
MT WT F S S
1 Feb 09
MT WT F S S
8 Feb 09
MT WT F S S
15 Feb 09
MT WT F S S
22 Feb 09
MT WT F S S
1 Mar 09
MT WT F S S
8 Mar 09
MT WT F S S
15 Mar 09
MT WT F S
*BRICKWORK
ROUGH INSPECTION
ELECTRICAL INSPECTION
**INSULATION
**INSULATION INSPECTION
*DRYWALL
INSTALL TRIM
*CASEWORK
*CLOSET
DELIVER CABINETS
INSTALL CABINETS
*TEMPLATE COUNTERTOPS
INSTALL APPLIANCES
DELIVER VANITIES
INSTALL VANITY
OD INT PAINT COLORS
OD EXT PAINT COLORS
S
22 Mar 09
MT WT F S S
29 Mar 09
MT WT F S S
5 Apr 09
MT WT F S S
12 Apr 09
MT WT F S S
19 Apr 09
MT WT F S S
26 Apr 09
MT WT F S S
3 May 09
MT WT F S S
10 May 09
MT WT F S S
17 May 09
MT WT
HVAC FINISH
PLUMBING FINISH
ELECTRICAL FINISH
SPEAKER FINISH
INSTALL FINISH HARDWARE
INSTALL COUNTERTOPS
INSTALL ACCESSORIES
MIRROR MEASURE
MIRROR INSTALL
MEASURE SHOWER DOORS
INSTALL SHOWER DOORS
CERAMIC TILE
INSTALL WOOD FLOOR
*CARPET
*VINYL FLOOR
*INT. PAINTING
*EXT PAINTING