Given the information provided below and the Gantt chart layout provided, you are to construct a Gantt chart, with overlaps as
specified.
Activity
L
e
t
t
e
r
Activity Description Predecessor
Duration
(months)
Overlap
(months)
A Train project team None 1 None
B Project paperwork and systems design A 2 ½ ¼
C Modify purchased package B 2 1
D Manual systems flow B 1 ½ 1
E Modify in-house procedures B 4 1
F Test and implement modifications to purchased package C 1 ½ 1/8
G Test and implement manual D ¾ 1/8
H Test and implement modifications to in-house procedures E 1 1/8
GANTT CHART EXERCISE
Schedule
Date Assigned: 12/7/87
Project No. 1016-1021 Project Title: Customer Index System
Assigned to: C.I. (Project Team)
Description December January February March April May June July
A. Train Project Team
B. Project Management Paperwork
C. Modify Purchased Package
D. Manual systems Flow
E. Modify In-House Procedures
F. Test and Implement Modifications to
Purchased Package
G. Test and Implement Manual Systems
Flow
H. Test and Implement Modifications to
In-House Procedrues
ANSWER KEY
GANTT CHART EXERCISE
Schedule
Date Assigned: 12/7/87
Project No. 1016-1021 Project Title: Customer Index System
Assigned to: C.I. (Project Team)
Description December January February March April May June July
A. Train Project Team
B. Project Management Paperwork
C. Modify Purchased Package
D. Manual systems Flow
E. Modify In-House Procedures
F. Test and Implement Modifications to
Purchased Package
G. Test and Implement Manual Systems
Flow
H. Test and Implement Modifications to
In-House Procedrues