Fillable Printable Standard Method Statement Template
Fillable Printable Standard Method Statement Template

Standard Method Statement Template

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Company Details
Company Name:
Noonan
Job LocationDIT, Bolton St
Description of
Task/Activity
Clean of external glazing
Glazing clean to be carried out using a Reach & WashSystem
Site/Building
Address
DIT
Permit Required
Details
General Works
Permits Required
Hot Work
Confined Space
Personnel Involved
Name
TBA
Site Supervisor
Wayne Gannon
Site Safety Officer
Division Manager
Fintan Lalor
Personnel Required
Certification
( E.g. Safe Pass,
MEWP Operator,
IRATA
International (Rope
Access))
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
Company Address:
Hilton House,
Unit 3,
Swords Business Park,
Swords,
Dublin.
industrial@noonan.ie
Document No. 204.2 Risk
Assessment
Attached
Clean of external glazing
within the courtyard area of the building.
Glazing clean to be carried out using a Reach & Wash System
, Bolton
Street,
Dublin
Start
Date/Time
TBA
Finish
Date/Time
Permit Number
Confined Space
Roof Access
General Works
MEWP
Name
Trade/Position
TBA
Wayne Gannon
Contact Number
0876775206
Contact Number
Fintan Lalor
Contact Number
0872331070
Human Focus Health and Safety Training (Industrial)
Suitably train and experienced Technicians
Tel:
01
-
8839800
Email:
industrial@noonan.ie
Yes
TBA
Access Permit
0876775206
0872331070

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Safety Method Statement
Works: Window Cleaning using Reach and Wash System,
Location: DIT, Bolton Street, Dublin.
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
Safety Method Statement
Noonan
Works: Window Cleaning using Reach and Wash System,
External Glazing within Courtyard.

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Company Details
Company Name:
Company Address:
Contact Number:
Contact Email:
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
Noonan
Noonan,
Hilton House,
Unit 3,
Swords Business Park.
Rep. of Ireland.
018839800
industrial@noonan.ie

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Company Contacts
Industrial Manager
Mr Fintan Lalor
Tel: 0872331070
Email: fintan.lalor@noonan.ie
Industrial Supervisor
Mr Wayne Gannon
Tel: 0876775206
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
WorkSite Details
Site Address
DIT,
Bolton Street,
Dublin.
Site Contacts
Site Agent/Facilities Manager:
Site Area Foreman:
Mr Wayne Gannon Tel: 0876775206
Site Safety Manager:
Site Emergency Contacts:
Mr Wayne Gannon Tel: 0876775206
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
Mr Wayne Gannon Tel: 0876775206
Mr Wayne Gannon Tel: 0876775206

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Noonan Industrial Division
Noonan operates under the
guideline and regulations set out below. We operate to the highest levels of
safety, and produce the end result required by the client.
•
HSA Saf
ety, Health and Welfare at Work (General Application)Regulation 2007
HSA Safety, Health and Welfare at work
Cleaning work in the allocated areas will be carried out to the client’s specification. This will be confirmed with
the client prior to commencement of works.
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
guideline and regulations set out below. We operate to the highest levels of
safety, and produce the end result required by the client.
ety, Health and Welfare at Work (General Application) Regulation 2007
.
HSA Safety, Health and Welfare at work
(General Applications) Regulation 2007
Cleaning work in the allocated areas will be carried out to the client’s specification. This will be confirmed with
the client prior to commencement of works.
guideline and regulations set out below. We operate to the highest levels of
Cleaning work in the allocated areas will be carried out to the client’s specification. This will be confirmed with

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Over Viewof Program of Works
This document covers the use of the
reach and wash
areas which the Lorry Mounted Hoist (LMH) cannot gain access
within the facility.
All Technicians operating
the reach and
The Technicians will be requir
ed to carry out the clean of the agreed upon
The works will be carried out under the aforementioned
The weather conditions will be monitored on a
The works will be carried out to the standard required by the client.
All accidents and incidents will be reported immediately to Facility Management and Noonan Management.
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
Over View ofProgram of Works
reach and wash
system to clean the external glazing of
the courtyard in
areas which the Lorry Mounted Hoist (LMH)cannot gain access
.
This will include the two main court yard areas
the reach and
wash system will be versed in its use.
ed to carry out the clean of the agreed upon
external glazing areas.
The works will be carried out under the aforementioned
safety documents.
The weather conditions will be monitored on a
n ongoing basis throughout the works.
The works will be carried out to the standard required by the client.
All accidents and incidents will be reported immediately to Facility Management and Noonan Management.
the courtyard in
This will include the two main court yard areas
external glazing areas.
All accidents and incidents will be reported immediately to Facility Management and Noonan Management.

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Requirements forProgram of Works
The program of works will require the
Noonan Technicians
be to the external court yard
to allow locating of the van and reach and wash trailer.
access to a water source.
The reach and wash system is trailer
mounted. With this in mind, a suitable location/s for the van
will be required.
Once located in the work site the equipment will be monitored closely by the Noonan Technicians. It will be
stored in a safe and correct manner a
s required both by the
Co-ordination between Noonan
Technicians,
the progression of the works. The areas below where the
be free of pedestrians. Other conflicting activities will also need to be monitored.
Monitoring of weather conditions will run throughout the program of works.
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
Requirements for Program of Works
Noonan Technicians
to have access t
o the base of the building.
to allow locating of the van and reach and wash trailer.
They will also require
mounted. With this in mind, a suitable location/s for the van
Once located in the work site the equipment will be monitored closely by the Noonan Technicians. It will be
s required both by the
Facility Management and Noonan.
Technicians,
Facility
Management and any third party will be essential during
the progression of the works. The areas below where the
Noonan
Technicians are working will be
be free of pedestrians. Other conflicting activities will also need to be monitored.
Monitoring of weather conditions will run throughout the program of works.
o the base of the building.
This will
They will also require
mounted. With this in mind, a suitable location/s for the van
and trailer
Once located in the work site the equipment will be monitored closely by the Noonan Technicians. It will be
Management and any third party will be essential during
Technicians are working will be
required to

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Conflicting Operations during Program of Works
The area below the Noonan
Technicians work space will be small and relatively easy to control in most areas.
This will be achieved using monitored barriers.
Any additional requirements from the
Facility
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
Conflicting Operations during Program of Works
Technicians work space will be smalland relatively easy to control in most areas.
This will be achieved using monitored barriers.
Facility
Management will be adhered to.
Technicians work space will be small and relatively easy to control in most areas.

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
Method of Works
The works are to be completed using
a reach and wash system
sequence.
1.
Site Specific induction completed by all technicians involved in the planned scope of works.
2.
All wo
rks to be carried out under Safety, Health and
Regulations 2007 and
Noonan
3.
Confirm all relevant permits and preliminary site paperwork is in place.
be on site. Acceptance of this document takes the form of a s
method statement.
4.
Visual inspection of work site in form of a ‘walk round’ byall team members. Locating of emergency
exits and relevant emergency
5.
Confirm scope of works with clients on site representat
6.
Identify the work space. Erect barriers where required to indicate work and prohibition.
7.
Confirm (in accordance with any permit requirement) the commencement of work.
8.
Confirm appropriate access and egress arrangements are in place.
9.
Locate the works van
and trailer
10.
Access to the work area will be
11.
Weather conditions will be assessed by the
works.
12.
The reach and wash system will be
13.
‘Buddy Check’ by all personnel on personal and group equipment.
14.
All work carried out
using the reach and wash system
manner.
15.
Access the work site and commence work.
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
a reach and wash system
and will be undertaken in the following
Site Specific induction completed by all technicians involved in the planned scope of works.
rks to be carried out under Safety, Health and
Welfare at Work (General Applications)
Noonan
Safe Working Procedure.
Confirm all relevant permits and preliminary site paperwork is in place.
A copy of this document will
be on site. Acceptance of this document takes the form of a s
ign in sheet found at the end of the
Visual inspection of work site in form of a ‘walk round’ by all team members. Locating of emergency
exits and relevant emergency
muster points.
Confirm scope of works with clients on site representat
ive.
Identify the work space. Erect barriers where required to indicate work and prohibition.
Confirm (in accordance with any permit requirement) the commencement of work.
Confirm appropriate access and egress arrangements are in place.
and trailer
in the agreed location.
Access to the work area will be
from the base of the building.
Weather conditions will be assessed by the
onsite
. This will be ongoing throughout the program of
The reach and wash system will be
inspected prior to mobilization to site.
‘Buddy Check’ by allpersonnel on personal and group equipment.
using the reach and wash system
must be completed in a safe and controlled
Access the work site and commence work.
and will be undertaken in the following
Site Specific induction completed by all technicians involved in the planned scope of works.
Welfare at Work (General Applications)
A copy of this document will
ign in sheet found at the end of the
Visual inspection of work site in form of a ‘walk round’ by all team members. Locating of emergency
Identify the work space. Erect barriers where required to indicate workand prohibition.
. This will be ongoing throughout the program of
must be completed in a safe and controlled

Method Statement/Risk Assessment
Number:204.2
Revision
Number:
16.
The
areas will be cleaned in a methodical manner.Each section willbe completed from the top down,
reducing the length of the reach and wash pole as it descends.
17.
Each time a move of the reach and wash system to a new location the technicians will check the
p
roposed location prior to moving.
18.
The reach and wash system will be used in a controlled manner to prevent injury to the technician
operating the system.
19.
Confirm acceptance of works prior t
20.
De-rig equipment from site.
21.
Remove all debris and waste material from work site and dispose in accordance with site regulations.
22.
Remove all barriers.
23.
Sign off permits.
Method Statement
Noonan
Issue Date: 16/05/11
Revision Date:
areas will be cleaned in a methodical manner. Each section willbe completed from the top down,
reducing the length of the reach and wash pole as it descends.
Each time a move of the reach and wash system to a new location the technicians will check the
roposed location prior to moving.
The reach and wash system will be used in acontrolled manner to prevent injury to the technician
Confirm acceptance of works prior t
o demobilizing/de-rigging equipment.
Remove all debris and waste material from work site and dispose in accordance with site regulations.
areas will be cleaned in a methodicalmanner. Each section will be completed from the top down,
Each time a move of the reach and wash system to a new location the technicians will check the
The reach and wash system will be used in acontrolled manner to prevent injury to the technician
Remove all debris and waste material from work site and dispose in accordance with site regulations.