Fillable Printable Contractor's Request for Information Template
Fillable Printable Contractor's Request for Information Template
                        Contractor's Request for Information Template

CONTRACTOR'S REQUEST FOR INFORMATION
DEFINITION: The construction documents (agreement, drawings and specifications), developed by
the Engineer, document the conditions agreed upon between the Owner and the Contractor. These
documents reflect the understanding that each party has with regard to constructing the Project 
they represent. If every set of Construction Documents were clear, unambiguous, and complete, 
interpretation would be unnecessary, as the intent and understanding of the parties would be self-
evident. Unfortunately, this is not always the case.
In most Construction Documents, it is inevitable that the agreement, drawings, and specifications 
will not adequately address every single matter. There may be gaps, conflicts, or subtle ambiguities.
The goal of the Request For Information (RFI) is to act as a partnering tool to resolve these gaps, 
conflicts, or subtle ambiguities during the bidding process or early in the construction process to 
eliminate the need for costly corrective measures. Should the response to the RFI lead to additional
work during the construction process that represents added value, which cannot be reasonably 
worked out in the early stages of the performance of the work, than a formal claim can be made?
Who submits: General Contractor
Who Responds: Engineer shall respond to all RFI's.
Contents: The RFI shall include the following:
During Bidding Phase
1. Reference to Specification and 
paragraph numbers, drawing 
numbers and drawing reference 
2. Identification of the clarification 
needed. 
3. Impact this clarification will have 
on schedule (number of days). 
During Construction Phase
1. Identification   of   the   construction   deficiency   or
Contract document clarification. 
2. Reference to Specification and paragraph 
numbers, drawing numbers and drawing 
reference. 
3. Impact this clarification will have on 
schedule (number of days) and project 
costs (if any). 
2. Categorize each RFI as follows: 
a. Substitution/Construction Modification 
b. Clarification or Additional Information 
c. Construction Deficiency (During Construction Phase). 
d. Construction Document Deficiency 
3. Substitution/Construction Modification 
a. During the Bidding Phase, a RFI for an equipment substitution or a Construction Modification
should be sent to the Engineer in writing at least 10 days prior to bid opening. (This request
will only be answered if request is from a General Contractor who is a plan holder.) 
b. During the Construction Phase an RFI for an equipment substitution or a Construction 
Modification should be submitted immediately attaching an appropriate form, if it is not, 
the Engineer should return to the Contractor. 
c. Engineer should take no action until the substitution request is received. 

d. Contractor shall identify the equipment substitution noting the specification or plan sheet
involved and the reason for the substitution. This would include schedule impacts and 
costs. 
e. Contractor shall identify the construction modification by detail and plan sheet location 
they are considering. The construction modification request shall outline the change 
requested in enough detail for the Engineer to review and the reasons for the change. Also
included would be schedule impacts and costs. 
3. Clarification or Additional Information 
a. Review the RFI request for completeness and return immediately if not complete. 
b. Review the RFI request and respond with the appropriate clarification or additional information. 
c. During the Construction phase, should the clarification or additions result in an impact
on schedule and project costs the Contractor will respond within 2 working days. 
d. No work is authorized until both schedule and project costs are agreed to. 
4. Construction Deficiency (During Construction Phase Only) 
a. If   the   RFI   is   about   a   construction   deficiency,   then   the   Engineer   should   complete   a
deficiency form and submit to the Contractor. 
b. This effort should be completed as soon as discovered or as determined from the RFI. 
c. The   deficiency   form   should   request   a   proposal   from   Contractor   on   how   to   correct   the
problem. 
5. Construction Document Deficiency 
a. Review RFI for verification of deficiency. 
b. Review RFI and respond with the proposed corrections to construction documents. 
c. Contractor   shall   review   schedule   and   cost   impact   within   2   working   days.   No   work   is
authorized until both schedule impact and project costs are agreed to. 
            
    
