Login

Fillable Printable Sample Risk Management Plan Template

Fillable Printable Sample Risk Management Plan Template

Sample Risk Management Plan Template

Sample Risk Management Plan Template

Risk Management Plan
Table of Contents
1 Executive Summary..........................................................................................................
1.1 Purpose...........................................................................................................................
2 Risk Management Strategy...............................................................................................
2.1 Risk Identification...........................................................................................................
2.2 Risk Responsibilities.......................................................................................................
2.3 Risk Assessment .............................................................................................................
2.4 Risk Response.................................................................................................................
2.5 Risk Mitigation ...............................................................................................................
2.6 Risk Contingency Planning.............................................................................................
2.7 Tracking and Reporting ..................................................................................................
2.8 Processes to Address Immediate Unforeseen Risks .......................................................
1 Executive Summary
Risk is defined as an event that has a probability of occurring, and could have either a positive or
negative impact to a project should that risk occur. A risk may have one or more causes and, if it
occurs, one or more impacts. For example, a cause may be requiring an environmental permit to
do work, or having limited personnel assigned to design the project. The risk event is that the
permitting agency may take longer than planned to issue a permit, or the assigned personnel
available and assigned may not be adequate for the activity. If either of these uncertain events
occurs, there may be an impact on the project cost, schedule or performance. All projects assume
some element of risk, and it’s through risk management where tools and techniques are applied
to monitor and track those events that have the potential to impact the outcome of a project.
Risk management is an ongoing process that continues through the life of a project. It includes
processes for risk management planning, identification, analysis, monitoring and control. Many
of these processes are updated throughout the project lifecycle as new risks can be identified at
any time. It’s the objective of risk management to decrease the probability and impact of events
adverse to the project. On the other hand, any event that could have a positive impact should be
exploited.
The identification of risk normally starts before the project is initiated, and the number of risks
increase as the project matures through the lifecycle. When a risk is identified, it’s first assessed
to ascertain the probability of occurring, the degree of impact to the schedule, scope, cost, and
quality, and then prioritized. Risk events may impact only one or while others may impact the
project in multiple impact categories. The probability of occurrence, number of categories
impacted and the degree (high, medium, low) to which they impact the project will be the basis
for assigning the risk priority. All identifiable risks should be entered into a risk register, and
documented as a risk statement.
As part of documenting a risk, two other important items need to be addressed.
The first is mitigation steps that can be taken to lessen the probability of the event occurring. The
second is a contingency plan, or a series of activities that should take place either prior to, or
when the event occurs. Mitigation actions frequently have a cost. Sometimes the cost of
mitigating the risk can exceed the cost of assuming the risk and incurring the consequences. It is
important to evaluate the probability and impact of each risk against the mitigation strategy cost
before deciding to implement a contingency plan. Contingency plans implemented prior to the
risk occurring are pre-emptive actions intended to reduce the impact or remove the risk in its
entirety. Contingency plans implemented after a risk occurs can usually only lessen the impact.
Identifying and documenting events that pose a risk to the outcome of a project is just the first
step. It is equally important to monitor all risks on a scheduled basis by a risk management team,
and reported on in the project status report.
1.1 Purpose
This plan documents the processes, tools and procedures that will be used to manage and control
those events that could have a negative impact on the Insert Project Name Here project. It’s the
controlling document for managing and controlling all project risks. This plan will address:
• Risk Identification
• Risk Assessment
• Risk Mitigation
• Risk Contingency Planning
• Risk Tracking and Reporting
Appendix A will present the risk impact assessment matrix and appendix B will present a sample
of the risk register.
2 Risk Management Strategy
2.1 Risk Identification
A risk is any event that could prevent the project from progressing as planned, or from successful
completion. Risks can be identified from a number of different sources. Some may be quite
obvious and will be identified prior to project kickoff.
Others will be identified during the project lifecycle, and a risk can be identified by anyone
associated with the project. Some risk will be inherent to the project itself, while others will be
the result of external influences that are completely outside the control of the project team.
The Insert Project Name Here Project Manager has overall responsibility for managing project
risk. Project team members may be assigned specific areas of responsibility for reporting to the
project manager.
Throughout all phases of the project, a specific topic of discussion will be risk identification. The
intent is to instruct the project team in the need for risk awareness, identification, documentation
and communication.
Risk awareness requires that every project team member be aware of what constitutes a risk to
the project, and being sensitive to specific events or factors that could potentially impact the
project in a positive or negative way.
Risk identification consists of determining which risks are likely to affect the project and
documenting the characteristics of each.
Risk communication involves bringing risk factors or events to the attention of the project
manager and project team.
The Insert Project Name Here project manager will identify and document known risk factors
during creation of the Risk Register.
It is the Insert Project Name Here project manager’s responsibility to assist the project team
and other stakeholders with risk identification, and to document the known and potential risks in
the Risk Register. Updates to the risk register will occur as risk factors change. Risk
management will be a topic of discussion during the regularly scheduled project meetings.
The Insert Project Name Here project team will discuss any new risk factors or events, and these
will be reviewed with the Insert Project Name Here project manager.
The project manager will determine if any of the newly identified risk factors or events warrant
further evaluation. Those that do will undergo risk quantification and risk response development,
as appropriate, and the action item will be closed.
At any time during the project, any risk factors or events should be brought to the attention of the
Insert Project Name Here project manager using Email or some other form of written
communication to document the item. The project manager is responsible for logging the risk to
the Risk Register. Notification of a new risk should include the following Risk Register
elements:
• Description of the risk factor or event, e.g. conflicting project or operational initiatives that
place demands on project resources, unexpected study outcomes, delays, etc.
• Probability that the event will occur. For example, a 50% chance that the vendor will not have
an animal colony that meets the criteria available.
• Schedule Impact. The number of hours, days, week, or months that a risk factor could impact
the schedule. As an example, the animals require an additional 3 months to meet age
requirements.
• Scope Impact. The impact the risk will have on the envisioned accomplishments of the project.
Delayed animal delivery may result in a reduction in the number of studies that can be completed
within the contract period of performance.
Quality Impact. A risk event may result in a reduction in the quality of work or products that
are developed. As an example, lack of funding caused by cost overruns may result in the
reduction of the study size and impact statistical empowerment
• Cost Impact. The impact the risk event, if it occurs is likely to have onthe project budget.
2.2 Risk Responsibilities
The responsibility for managing risk is shared amongst all the stakeholders of the project.
However, decision authority for selecting whether to proceed with mitigation strategies and
implement contingency actions, especially those that have an associated cost or resource
requirement rest with the Project Manager who is responsible for informing the funding agency
to determine the requirement for a contract modification. The following tables details specific
responsibilities for the different aspects of risk management.
Risk Activity Responsibility
Risk Identification: All project stakeholders
Risk Registry: Project Manager
Risk Assessment: All project stakeholders
Risk Response Options Identification: All project stakeholders
Risk Response Approval: PM with concurrence from CO/PO/COTR
Risk Contingency Planning; Project Manager(s)
Risk Response Management; Project Managers
Risk Reporting; Project Manager
2.3 Risk Assessment
Risk assessment is the act of determining the probability that a risk will occur and the impact that
event would have, should it occur. This is basically a “cause and effect” analysis. The “cause” is
the event that might occur, while the “effect” is the potential impact to a project, should the event
occur.
Assessment of a risk involves two factors. First is the probability which is the measure of
certainty that an event, or risk, will occur. This can be measured in a number of ways, but for the
Insert Project Name Here project will be assigned a probability as defined in the table below.
Probability of Occurrences
Definition
Meaning
Value
Frequent
Occurs frequentl y
Wil l be cont inu ous ly ex per ienced unless
action is taken to change events
5
Likely
Occur less frequently if process is corrected
Issues ide ntif ied w ith min imal audit activity
Proce ss perfor man ce fail ur e s ev ident to
trained auditors or regulators
4
Occasional
Occurs sporadically
Potenti al is sue s discov er ed du ring focu sed
review.
3
Seldom
Unlikely to occur
Minimal issue identification during focused
review
2
Improbable
Highly unlikely to occur
1
The second factor is estimate of the impact on the project. This can be a somewhat subjective
assessment, but should be quantified whenever possible. The estimated cost, the duration of the
potential delay, the changes in scope and the reduction in quality are in most cases factors that
can be estimated and documented in the risk statement and then measured using the standard
project management tools (i.e. project plan, budget, statements of work). Rather than detailed
impact estimates the Risk Register contains five ratings for impact;
Catastrophic (A)
Regulatory/Compliance violations/issues
Inability to validate data
Withdrawal of product manufacturer
Tainted product
Materials breech
Production delays
Technical miscommunications
Security/confidentiality breeches
Critical (B)
A non-compliance finding resulting in process, or operational degradation
A security finding requiring immediate corrective action prior to continued operation
Reoccurring violation of any safety regulation resulting in serious injury
Production errors containing regulatory violations that pose direct consequence to the operation
Mod erate (C)
Security finding requiring a Corrective Action Plan
Production element errors that may pose indirect consequences to the operation
Minor (D)
No regulatory action anticipated
No compliance impact anticipated
No evident security threat affected
Minor errors in completed Company policy & procedures
Production errors containing quality system and / or opportunities for improvement
Negligible (E)
No regulatory/compliance violation
No security/confidentiality element affected
On time production
Validated experiments
“Clean” product
Properly executed communications
For each of the impact categories the impact assessment should include consideration of the
following areas of impact also:
• Cost – This impact is usually estimated as a dollar amount that has a direct impact to the
project. However, cost is sometimes estimated and reported as simply additional resources,
equipment, etc. This is true whenever these additional resources will not result in a direct
financial impact to the project due to the fact the resources are loaned or volunteer, the
equipment is currently idle and there is no cost of use, or there are other types of donations that
won’t impact the project budget. Regardless of whether there is a direct cost, the additional
resources should be documented in the risk statement as part of the mitigation cost.
• Scope – Whenever there is the potential that the final product will not be completed as
originally envisioned there is a scope impact. Scope impact could be measured as a reduction of
the number of studies completed, or not providing a deliverable such as an IND.
• Schedule – It is very important to estimate the schedule impact of a risk event as this often
results is the basis for elevating the other impact categories. Schedule delays frequently result in
cost increases and may result in a reduction of scope or quality. Schedule delays may or may not
impact the critical path of the project and an associated push out of the final end date.
Performance/QualityPerformance/Quality is frequently overlooked as an impact category
and too often a reduction in quality is the preferred choice for mitigation of a risk. “Short cuts
and “low cost replacements” are ways of reducing cost impacts. If not documented appropriately
and approved by the project sponsor, mitigation strategies that rely upon a reduction in quality
can result in significant disappointment by the stakeholders.
Most risks will be assigned one category, but some might be assigned more than one, or all.
2.4 Risk Response
For each identified risk, a response must be identified. It is the responsibility of the project team
to select a risk response for each risk. The proj e ct t eam will need the best possible assessment of
the risk and description of the response options in order to select the right response for each ri sk .
The probability of the risk event occurring and the impacts will be the basis for determining the
degree to which the actions to mitigate the risk should be taken. One way of evaluating
mitigation strategies is to multiply the risk cost times the probability of occurrence. Mitigation
strategies that cost less than risk probability calculation should be given serious consideration.
The possible response options are:
• Avoidance – Change the project to avoid the risk. Change scope, objectives, etc.
• Transference – Shift the impact of a risk to a third party (like a subcontractor). It does not
eliminate it, it simply shifts responsibility.
• Mitigation – Take steps to reduce the probability and/or impact of a risk. Takin g early action,
close monitoring, more testing, etc.
• Acceptance Simply accept that this is a risk. When choosing acceptance as a response the
IMPD is stating that given the probability of occurring and the associated impact to the project
that results, they are not going to take any actions and will accept the cost, schedule, scope, and
quality impacts if the risk event occurs.
• Deferred – A determination of how to address this risk will be addressed at a later time. The
results of the risk assessment process are documented in each Risk Statement and summarized in
the Risk Register which will be reported on a monthly basis.
2.5 Risk Mitigation
Risk mitigation involves two steps:
• Identifying the various activities, or steps, to reduce the probability and/or impact of an adverse
risk.
• Creation of a Contingency Plan to deal with the risk should it occur.
Taking early steps to reduce the probability of an adverse risk occurring may be more effective
and less costly than repairing the damage after a risk has occurred. However, some risk
mitigation options may simply be too costly in time or money to consider.
Mitigation activities should be documented in the Risk Register, and reviewed on a regular basis.
They include:
• Id entification of potential failure points for each risk mitigation solution.
• For each failure point, document the event that would raise a “flag” indicating that the event or
factor has occurred or reached a critical condition.
• For each failure point, provide alternatives for correcting the failure.
2.6 Risk Contingency Planning
Contingency planning is the act of preparing a plan, or a series of activities, should an adverse
risk occur. Having a contingency plan in place forces the project team to think in advance as to a
course of action if a risk event takes place.
• Identify the contingency plan tasks (or steps) that can be performed to implement the mitigation
strategy.
• Identify the necessary resources such as money, equipment and labor.
• Develop a contingency plan schedule. Since the date the plan will be implemented is unknown,
this schedule will be in the format of day 1, day 2, day 3, etc., rather than containing specific
start and end dates.
• Define emergency notification and escalation procedures, if appropriate.
• Develop contingency plan training materials, if appropriate.
• Review and update contingency plans if necessary.
• Publish the plan(s) and distribute the plan(s) to management and those directly involved in
executing the plan(s).
Contingency may also be reflected in the project budget, as a line item to cover unexpected
expenses. The amount to budget for contingency may be limited to just the high probability risks.
This is normally determined by estimating the cost if a risk occurs, and multiplying it by the
probability. For example, assume a risk is estimated to result in an additional cost of $50,000,
and the probability of occurring is 80%. The amount that should be included in the budget for
this one item is $40,000.
Associated with a contingency plan, are start triggers and stop triggers. A start trigger is an ev ent
that would activate the contingency plan, while a stop trigger is the criteria to resume normal
operations. Both should be identified in the Risk Register and can be embedded, example; the
stop trigger can be included in the contingency plan field.
2.7 Tracking and Reporting
As project activities are conducted and completed, risk factors and events will be monitored to
determine if in fact trigger events have occurred that would indicate the risk is now a reality.
Based on trigger events that have been documented during the risk analysis and mitigation
processes, the project team or project managers will have the authority to enact contingency
plans as deemed appropriate. Day to day risk mitigation activities will be enacted and directed by
the project managers.
Contingency plans that once approved and initiated will be added to the project work plan and be
tracked and reported along with all of the other project activities.
Risk management is an ongoing activity that will continue throughout the life of the project. This
process includes continued activities of risk identification, risk assessment, planning for newly
identified risks, monitoring trigger conditions and contingency plans, and risk reporting on a
regular basis. Project status reporting contains a section on risk management, where new risks
are presented along with any status changes of existing risks. Some risk attributes, such as
probability and impact, could change during the life of a project and this should be reported as
well.
2.8 Processes to Address Immediate Unforeseen Risks
The individual identifying the risk will immediately notify the project managers. The individual
notified will assess the risk situation.
If required, the project managers will identify a mitigating strategy, and assign resources as
necessary.
The project risk manager will document the risk factor and the mitigating strategy.
Appendix A Example Risk Assessment Matrix
Probability of Occurrences
Catastrophic
Critical
Minor
Negligible
Definition
Meaning
Value
(A)
(B)
(D)
(E)
Frequent
Occurs
frequently
Will be
continuously
experienced
unless
action is
taken to
change
events
5
5A 5B 5C 5D 5E
Likely
Occur less
frequently if
process is
corrected
Issues
identified
with minimal
audit activity
Process
performance
failures
evident to
trained
auditor s or
regulators
4
4A 4B 4C 4D 4E
Occasional
Occurs
sporadically
Potential
issues
discovered
during
focused
review.
3
3A 3B 3C 3D 3E
Seldom
Unlikely to
occur
Minimal
issue
identification
during
focused
review
2
2A 2B 2C 2D 2E
Improbable
Highly
unlikely to
occur
1
1A 1B 1C 1D 1E
Ri sk Level s:
Risk is High for codes 5A, 5B, 5C, 4A, 4B, 3A
Risk is Medium High for codes 5D, 5E, 4C, 3B, 3C, 2A, 2B
Risk is Medium Low for codes 4D, 4E, 3D, 2C, 1A, 1B
Risk is Low for codes 3E, 2D, 2E, 1C, 1D, 1E
Appendix B – Example Risk Register
Ri sk Regist er f or "G ener i c Vaccine"
Gantt
WBS Risk Ove rall Impact Mitigation Contingency CSP Im pact Ti m ing / Opti on
Additional
30 1.3.2.4
FDA does not agree wi t h the
characteri zat i on resul t s (non-cl i ni cal
and cl i ni cal studi es pl anned, exam pl e
i f F DA requires NHP instead of used
ani m al m odel )
Occasi onal +
M oderat e = 3C
E arl y and frequent m eeti ngs wi t h the
FDA pri or t o study executi on.
Updat e program des i gn wi t h F DA
i nput , m odi fy S O W, obtai n B ARDA
CO, PO , and M anagem ent A pproval of
new S OW, and provi de budget request
$400, 000 for NHP
M odel S tudy
A ddi ti on of ~ 9
months
Q3, FY11 - BASE
Lab unabl e t o produce an adequat e
am ount of produc t to conduct al l
studi es that are current l y schedul ed
S ubcontract negoti at i ons wi t h CM O to
produc e product for us e i n non-cl i ni cal
studies.
2. Use avai labl e l ab product unti l CRO
1.
S l ow t he pace of t he studi es to
accom m odate t he producti on
availability
cG M P product i s avai l abl e
1.
Us e avai l abl e l ab produc t and
schedul e st udi es based on avai l abl e
product.
2.
Transi t i on financi al res ources from
Cont ract negot i ati ons fail ure
S ubcontract negoti at i ons wi t h CM O to
produc e non-GM P produc t for use i n
non-c l i ni cal studi es.
subcontrac t to expansi on of l ab for
production.
3. Trans i ti on fi nanci al res ources to
ex
pedi t e the executi on of the cGMP
subcontract.
1.
S econd m anufac turi ng attem pt
2.
Discont i nue contrac t and use l ab
M anufact uri ng fail ure
Compl ete t echni cal package and
assi st ance avai l abl e from l ab.
product
3.
Discont i nue contrac t and expedi t e
t he cGM P m anufacturi ng cont ract.
Cont ract negot i ati ons fail ure wi t h
c GMP facilit y
E arl y RF P for evaluati on of mul ti ple
CMO fac ilit ies
A l ternate faci l i t y RFP
Tech Transfer fail ure (lack of det ai led
information)
Compl eti on of detai l ed m anufac turing
t echni cal t ransfer package and SM E
provisi ons duri ng pil ot l ot preparati ons
M anufact uri ng process devel opm ent,
t esti ng, opti m i z ati on and val i dat i on
requirement
S tudy Task 2 (subt ask st udi es task
l i nes 37 and 38) coul d yi eld negati ve
res ul ts, not m eet success cri teria
P rel i m i nary studi es conduct ed wi th
posi ti ve res ul ts
A l ternate study desi gn and potent i al
produc t redesi gn
S tudy Task 1 (subt ask st udi es task
l i nes 45 and 46) coul d yi eld negati ve
res ul ts, not m eet success cri teria
P rel i m i nary studi es conduct ed wi th
posi ti ve res ul ts
A l ternate study desi gn and potent i al
produc t redesi gn
S tudy Task 3 (subt ask st udi es task
l i nes 52, 53, 54, and 55) c oul d yi el d
negat i ve resul t s, not m eet success
criteria
P rel i m i nary studi es conduct ed wi th
posi ti ve res ul ts
A l ternate study desi gn and potent i al
produc t redesi gn
Login to HandyPDF
Tips: Editig or filling the file you need via PC is much more easier!
By logging in, you indicate that you have read and agree our Terms and Privacy Policy.