Login

Fillable Printable Audit Report - US Department of Energy

Fillable Printable Audit Report - US Department of Energy

Audit Report - US Department of Energy

Audit Report - US Department of Energy

AUDIT REPORT
Security Improvements at the Y-12 National
Security Complex
DOE/IG-0944
August 2015
U.S. Department of Energy
Office of Inspector General
Office of Audits and Inspections
Departm e nt of Energy
Washington, DC 20585
August 28, 2015
MEMORANDUM FOR THE SECRETARY
FROM: Gregory H. Friedman
Inspector General
SUBJECT: INFORMATION: Audit Report: "Security Improvements at the Y-12
National Security Complex"
BACKGROUND
The Y-12 National Security Complex (Y-12) is a manufacturing facility that plays a vital role in
the Department of Energy's nuclear security and weapons enterprise. Activities at Y-12 include
retrieving and storing nuclear materials, helping fuel the Nation's naval reactors, and performing
complementary work for other Government and private-sector entities. In June 2004, the Office
of Inspector General's report on Management of the Department's Personnel Security and Access
Control Information Systems (DOE/IG-0651) recommended that the Department develop a
comprehensive framework for managing and integrating personnel security and access control
systems.
In response to the report, the National Nuclear Security Administration (NNSA) indicated that it
intended to implement the Argus security system to provide integrated access and physical
security controls at Y-12. To help meet its security goals, Y-12 focused its planned Security
Improvements Project (SIP) on replacing its aged and obsolete security system with Argus. The
project was completed in 2013 at a cost of more than $50 million.
Because of the sensitivity of Y-12 and the material it houses, we initiated this audit to determine
whether the complex fully and effectively implemented improvements to meet its security needs.
RESULTS OF AUDIT
Our review found that the SIP was implemented within the established schedule and budget, and
it achieved all baseline requirements. However, we found that the SIP was not scoped or funded
to address all Argus implementation issues at Y-12. As a result, while Y-12 spent more than $50
million to upgrade its physical security system, it had not met NNSA's mandate to develop and
implement a comprehensive method for managing and integrating the site's security and access
control systems. In particular, our review revealed the following:
Although Y-12 initially identified the need to streamline its physical security
environment, we found that officials had not utilized all available Argus functionality to
2
achieve this goal. For instance, Y-12 was only using Argus' Homeland Security
Presidential Directive 12 (HSPD-12) technology to manage physical access to
approximately 1 percent of the site. In addition, NNSA could not fully fund all available
Argus functionality. As a result, Y-12 was forced to rely on its existing Identity
Verification System, which could not be integrated with Argus, to provide access control
to the rest of the site.
While the Argus implementation originally proposed to meet NNSA's mandate by
updating all security infrastructure components, officials did not replace certain system
components, such as the legacy alarm wiring cabinets and sensors. This resulted in
compatibilit y issues and significantl y increased the number of false or nui s ance al arm s
that operators received. Alarm station operators told us they were not able to efficiently
perform their duties because they had to repeatedly address nuisance alarms.
Local site map design issues within Argus resulted in various errors that negatively
affected the efficiency of Y-12's security and alarm operations. For instance, the system's
site-level maps included many unnecessary elements, such as parking lots, which
cluttered the visual fields, negatively affecting operator response time and hampering
situational awareness. Location labels within the maps were also di ffe rent fro m the
legacy system information, creating a significant learning curve for the console operators.
NNSA and Y-12 officials encountered a number of challenges that affected the ability to fully
implement needed security upgrades. Perhaps one of the most significant challenges was the
need for NNSA officials to balance the requirement to install Argus with available resources.
This ultimately drove decisions regarding the system's implementation approach and limited the
use of HSPD-12 technology to enhance physical access controls throughout the site. However,
even within the confines of the effort's funding limitations, we found that management
weaknesses existed that contributed, at least in part, to the issues identified with the
implementation of the securi ty enhanc emen ts . In particular, a lack of effective communication
and cooperation between operations personnel and project managers contributed to the identified
system issues.
Y-12 officials told us that they gained a better understanding of the shortcomings with their
implementation of the Argus system and had initiated steps to achieve full system functionality.
In addition, Y-12 hired a team of subject matter experts in 2012 to review its Argus
implementation. This team of experts issued a report that identified the need to reengineer
certain components of the original installation. While reengineering appeared to be necessary to
address existing system shortcomings, such actions will take considerable time and resources. In
the intervening period, Y-12's security posture will be challenged by prolonged high rates of
nuisance alarms and a series of security processes that are overly complicated.
Site officials indicated that until funding is available and deficiencies in the legacy infrastructure
can be addressed, they will continue to compensate for the deficiencies by using additional
personnel at significant additional cost. In light of the issues identified, we made several
recommendations that, if fully implemented, should aid NNSA and Y-12 in further improving
the site's security posture.
3
MANAGEMENT RESPONSE
Management concurred with the report's recommendations and indicated that corrective actions
had been initiated or were planned to address the issues identified in the report. Management's
response, planned actions, and estimated timeframe for completion are responsive to our
recommendations. Management's comments and our responses are summarized in the body of
the report. Management's formal comments are included in their entirety in Appendix 3.
Attachments
cc: Deputy Secretary
Administrator, National Nuclear Security Administration
Chief of Staff
AUD IT REP ORT : SECURITY IMPROVEMENTS AT THE Y-12
NATIONAL SECURITY COMPLEX
TABLE O F CO NTE NTS
Audit Report
Details of Finding .......................................................................................................................... 1
Recommendations .......................................................................................................................... 5
Management Response and Auditor Comments ............................................................................ 6
Appendices
1. Objective, Scope, and Methodology .................................................................................. 7
2. Prior Reports ...................................................................................................................... 9
3. Management Comments .................................................................................................. 11
SECURITY IMPROVEMENTS AT THE Y-12 NATIONAL
SECURITY COM PLEX
Details of Finding Page 1
DETAILS O F FINDI NG
In June 2004, the Office of Inspector General's report on Management of the Department's
Personnel Security and Access Control Information Systems (DOE/IG-0651) recommended that
a comprehensive framework for managing and integrating personnel security and access control
systems be developed across the Department of Energy (Department). In response, National
Nuclear Security Administration (NNSA) management indicated that the Argus system, which
was developed by the Lawrence Livermore National Laboratory, would be the standard system
for integrating alarm monitoring and access control at its sites. To meet this mandate, in 2004,
the Y-12 National Security Complex (Y-12) focused its Security Improvements Project (SIP) on
replacing its legacy alarm system through the implementation of Argus.
Our review found that the SIP was implemented within its established schedule and budget and
met all of its baseline requirements. However, the Argus system as installed at Y-12 did not
fully meet the site's security needs and, in some cases, had not been effectively implemented.
Y-12 spent more than $50 million to upgrade its physical security system; however, the site had
not met NNSA's mandate to develop and implement a comprehensive method for managing and
integrating the site's security and access control systems. In particular, while the need to
streamline the physical security environment h ad b een identified, we found that NNSA was not
able to fully fund all available Argus functionality and as such, continued to rely upon a separate
system to provide access control to the areas of the site not controlled by Argus. In additi on, the
use of legacy infrastructure components with Argus resulted in compatibility issues that
significantly increased the number of false and nuisance alarms. Furthermore, local system map
design and labeling issues resulted in various errors related to the site's security environment that
affected operator response time and situational awareness, and affected the efficiency of the site's
security and alarm operations.
Access Control Systems
Although Y-12 had identified the need to streamline its physical security environment, we found
that it had not utilized all available Argus functionality. As a result, Y-12 officials maintained a
separate system to provide access control to certain areas of the site not controlled by Argus. For
instance, even though Y-12 officials required that Argus provide Homeland Security Presidential
Directive 12
1
(HSPD-12) functi onalit y, we found that the site was only using this technology to
manage physical access to approximately 1 percent of its buildings. In addition, Y-12 upgraded
its in-house developed Identity Verification System at a cost of more than $1 million to provide
automated access control to areas protecting special nuclear material that were not controlled by
Argus. The Identity Verification System could not be integrated with Argus, which resulted in
an increased workload for the security console operators. By not implementing an integrated
solution, Y-12 not only limited Argus' usefulness as a comprehensive security solution, but also
1
HSPD-12 required the use of identificatio n that meets the Presidential Directive's Sta nd a rd for Federal employees
and contractors in gaining physical access to federa lly controlled facilities. The Standard required that identification
be (a) issued based on sound crit eri a for verifying an individual empl oyee's identi ty; (b ) strongly resista nt to identity
fraud , tampering, co unterfeiting, and ter rorist exp loitation; (c) r a pidly authenticate d electr onically; and (d) issued
only by p r ovid er s whose reliability has been establi shed by an official accreditation process.
Details of Finding Page 2
performed work that was contrary to NNSA's mandate to install an integrated access control and
intrusion detection system. Had Y-12 fully implemented the Argus system, the site's security
needs may have been more effectively and efficiently met.
Legacy Infrastructure
Although originally proposed to meet NNSA's mandate by updating all security infrastructure
components, Y-12 ultimately did not replace the site's legacy alarm wiring cabinets and other
system components (such as sensors) when installing Argus. The legacy alarm cabinets provided
the wiring to all alarm sensors controlled by the site's security system. Argus' increased
sensitivity as compared to the legacy system resulted in an increase in false or n ui sance al arm s of
nearly 25 percent upon implementation. Steps were taken to reduce the false/nuisance alarm rate
subsequent to an intrusion at the site in July 2012. However, our analysis of 27 months of alarm
data (May 2012 to July 2014) determined that these types of alarms, on average, accounted for
more than 35 percent of those received, assessed, and closed by the alarm station operators on a
monthly basis. As such, the operators stated that they were less able to efficiently perform their
duties because they were repeatedly distracted by false/nuisance alarms.
NNSA management acknowledged that false and nuisance alarms were driven by the legacy
alarm sensors, which were not replaced during the Argus implementation. Management also
stated that NNSA continued to replace the sensors that have historically demonstrated a higher
false or nuisance alarm rate. We are encouraged by management's efforts in this area and
suggest efforts continue to aggressively monitor and reduce alarm rates, to include any ongoing
Argus sensitivity issues and replacing system components that are contributing to increased
alarm rates.
Sys tem Mapping a nd Labeling
Local site map design issues within Argus resulted in various errors that negatively affected the
efficiency of Y-12's security and alarm operations. For instance, the system's site-level maps
included many unnecessary elements, such as parking lots, which cluttered the visual fields,
affecting operator response time and situational awareness. Location labels within the maps
were also different from the legacy system information, creating a significant learning curve for
the console operators. Although management stated that these issues had not been raised prior to
placing the system into the production environment, we obtained evidence that concerns were
raised as early as June 2011almost 6 months prior to the start of system transition. In addition,
the system owner was provided a list of almost 150 discrepancies in September 2011. One
month later, the list had grown to almost 200 issues, 36 of which were deemed to be critical to
the system's functionality. However, when the issues were brought to the project manager's
attention, they were deferred to be addressed after the transition was complete and the system
was in production. Security officials were also asked not to raise the issues at the daily project
meetings. Remediation for a number of the issues began after the start of our test work. In
particular, the maps were updated to remove many of the unnecessary elements. However, at the
time of our review, nearly half of the significant issues had not been resolved.
Details of Finding Page 3
Funding and Management Challenges
NNSA and Y-12 officials encountered a number of challenges that affected the ability to fully
implement needed security upgrades. According to NNSA officials, the need to balance the
requirement to install Argus with available resources ultimately drove decisions regarding the
system's implementation approach. In particular, despite NNSA's mandate to install Argus, it
only made $80 million available for the project. This decision required reduction of the project's
scope to exclude certain infrastructure upgrades such as wiring cabinets and sensors.
Replacement of these elements would have allowed installed Argus components to function
more effectively. Such decisions also limited the use of HSPD-12 technology throughout the
site.
Even within the confines of NNSA's funding limitations, we found that management weaknesses
contributed, at least in part, to the issues identified. For example, although NNSA had developed
an analysis to identify remaining gaps in upgrading the security posture at Y-12, a detailed plan
and schedule for implementing the enhancements had not been developed. In addition, a review
conducted by the site identified the need to rework its Argus implementation. The review
estimated that approximately $300 million will be needed to fully address the site's security
needs and implement Argus as its integrated access control and physical security solution.
However, in commenting on our report, NNSA officials stated that the actual cost to fully
implement Argus was unknown. Plans, schedules, and cost estimates are critical for ensuring the
site's remaining security needs are effectively addressed.
In addition, NNSA developed a Stakeholders Communications Plan for the Y-12 National
Security Complex Security Improvement Project, which was meant to provide a communication
strategy to support effective decision making and exchange of information concerning the
project. However, we identified concerns related to a lack of effective communication and
cooperation between operations personnel and project managers that contributed to decreased
system functionality. For example, some system users asserted that the project's timely
implementation was frequently put ahead of system performance, resulting in operating
inefficiencies related to system mapping and labeling and false/nuisance alarms. Management
stated that trade-offs must be made to balance timely implementation with the significance and
impact of issues raised. It acknowledged that some users may have interpreted this as putting
timely implementation ahead of performance. While we recognize that timely implementation
and system performance can be conflicting objectives, we disagree that the degree of reduced
system performance experienced constituted a reasonable trade-off for timely implementation.
In either case, the system's performance was so poor that both current project management and a
consulting team of subject matter experts determined the need for extensive reengineering.
Management and experts concluded that significant additional funds would be required to
upgrade the site's security infrastructure, including installation of hardware such as badge
readers, cabling, and alarm cabinets. While not all of the team's conclusions were related to
issues initially raised by the system's users, they are lessons that should be considered and
applied to future upgrades.
Details of Finding Page 4
Future Upgrades
As noted, the Y-12 Argus system was not implemented to function as the site's comprehensive
access control and security monitoring solution, as required by NNSA. In late 2012, Y-12 spent
nearly $1.3 million for a consultant to review the system's implementation and determine what
steps should be taken to ensure that it provided full functionality to the site. The review
determined the need to reconfigure and deploy the system as an integrated security and access
control solution with the level of functionality and interaction needed. Fo r ex am pl e, much of the
Argus system was built upon the site's aging legacy infrastructure, which will need to be
modified and replaced to enable the system to fully meet the site's security needs in the most
efficient manner. In the meantime, the system's operators continue to compensate for the
system's shortcomings with an already limited workforce.
Prolonged high rates of false or nuisance alarms could lead to morale problems among system
operators. In particular, the site's alarm station operators are charged with receiving, assessing,
and providing disposition for alarms received to ensure the protection of Y-12's personnel and
materials. Due to the importance of their role in the overall security mechanism, management
must ensure that this group does not become complacent and maintains a high morale. We
recognize the ongoing challenges NNSA faces in implementing Argus at Y-12. However, given
the high importance of the Y-12 mission and in the wake of a physical security incident at the
site in 2012, NNSA should aggressively develop and fully implement a plan to achieve that goal
and address any remaining issues in this area.
Recommendations Page 5
RECOMMENDATIONS
To help improve the management of physical security, we recommend that the Administrator,
National Nuclear Security Administration direct the NNSA Production Office, in conjunction
with Y-12 National Security Complex Management, to:
1. Identify, consider, and address all critical security needs not addressed in the Argus
implementation through the development and full implementation of comprehensive
analyses, plans, schedules, and budgets;
2. Identify, evaluate, and repair or replace all security system components that are
contributing to high false or nuisance alarm rates; and
3. Ensure the appropriate dissemination and use of lessons learned, as outlined in this report
and in the SIP completion report.
Management Response and Auditor Comments Page 6
MANAGEMENT RESPONSE
Management concurred with each of the report's recommendations and indicated that corrective
actions had been initiated or were planned to address the identified issues. For instance,
management commented that NNSA and Y-12 officials are working to identify, prioritize, and
address the security needs of Y-12 within programmatic constraints. In addition, management
noted that it is taking an active role in monitoring and trending alarm maintenance timelines and
associated compensatory measure data to identify and resolve problem areas. Furthermore,
management stated that it will review and consider the findings of this report, along with other
lessons learned reports already produced, in any future Argus installations.
AUDITO R COM MENTS
Management's response, planned actions, and estimated timeframe for completion are responsive
to our recommendations. Management's comments are included in Appendix 3.
Login to HandyPDF
Tips: Editig or filling the file you need via PC is much more easier!
By logging in, you indicate that you have read and agree our Terms and Privacy Policy.