Login

Fillable Printable Test Plan Outline

Fillable Printable Test Plan Outline

Test Plan Outline

Test Plan Outline

IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 1
TEST PLAN OUTLINE
(IEEE 829 FORMAT)
1) Test Plan Identifier
2) References
3) Introduction
4) Test Items
5) Software Risk Issues
6) Features to be Tested
7) Features not to be Tested
8) Approach
9) Item Pass/Fail Criteria
10) Suspension Criteria and Resumption Requirements
11) Test Deliverables
12) Remaining Test Tasks
13) Environmental Needs
14) Staffing and Training Needs
15) Responsibilities
16) Schedule
17) Planning Risks and Contingencies
18) Approvals
19) Glossary
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 2
IEEE TEST PLAN TEMPLATE
1 TEST PLAN IDENTIFIER
Some type of unique company generated number to identify this test plan, its level and the
level of software that it is related to. Preferably the test plan level will be the same as the
related software level. The number may also identify whether the test plan is a Master plan, a
Level plan, an integration plan or whichever plan level it represents. This is to assist in
coordinating software and testware versions within configuration management.
Keep in mind that test plans are like other software documentation, they are dynamic in nature
and must be kept up to date. Therefore, they will have revision numbers.
You may want to include author and contact information including the revision history
information as part of either the identifier section of as part of the introduction.
2 REFERENCES
List all documents that support this test plan. Refer to the actual version/release number of
the document as stored in the configuration management system. Do not duplicate the text
from other documents as this will reduce the viability of this document and increase the
maintenance effort. Documents that can be referenced include:
!" Project Plan
!" Requirements specifications
!" High Level design document
!" Detail design document
!" Development and Test process standards
!" Methodology guidelines and examples
!" Corporate standards and guidelines
3 INTRODUCTION
State the purpose of the Plan, possibly identifying the level of the plan (master etc.). This is
essentially the executive summary part of the plan.
You may want to include any references to other plans, documents or items that contain
information relevant to this project/process. If preferable, you can create a references section
to contain all reference documents.
Identify the Scope of the plan in relation to the Software Project plan that it relates to. Other
items may include, resource and budget constraints, scope of the testing effort, how testing
relates to other evaluation activities (Analysis & Reviews), and possible the process to be
used for change control and communication and coordination of key activities.
As this is the “Executive Summary” keep information brief and to the point.
4 TEST ITEMS (FUNCTIONS)
These are things you intend to test within the scope of this test plan. Essentially, something
you will test, a list of what is to be tested. This can be developed from the software
application inventories as well as other sources of documentation and information.
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 3
This can be controlled and defined by your local Configuration Management (CM) process if
you have one. This information includes version numbers, configuration requirements where
needed, (especially if multiple versions of the product are supported). It may also include key
delivery schedule issues for critical elements.
Remember, what you are testing is what you intend to deliver to the Client.
This section can be oriented to the level of the test plan. For higher levels it may be by
application or functional area, for lower levels it may be by program, unit, module or build.
5 SOFTWARE RISK ISSUES
Identify what software is to be tested and what the critical areas are, such as:
A. Delivery of a third party product.
B. New version of interfacing software
C. Ability to use and understand a new package/tool, etc.
D. Extremely complex functions
E. Modifications to components with a past history of failure
F. Poorly documented modules or change requests
There are some inherent software risks such as complexity; these need to be identified.
A. Safety
B. Multiple interfaces
C. Impacts on Client
D. Government regulations and rules
Another key area of risk is a misunderstanding of the original requirements. This can occur at
the management, user and developer levels. Be aware of vague or unclear requirements and
requirements that cannot be tested.
The past history of defects (bugs) discovered during Unit testing will help identify potential
areas within the software that are risky. If the unit testing discovered a large number of
defects or a tendency towards defects in a particular area of the software, this is an indication
of potential future problems. It is the nature of defects to cluster and clump together. If it
was defect ridden earlier, it will most likely continue to be defect prone.
One good approach to define where the risks are is to have several brainstorming sessions.
!" Start with ideas, such as, what worries me about this project/application.
6 FEATURES TO BE TESTED
This is a listing of what is to be tested from the USERS viewpoint of what the system does.
This is not a technical description of the software, but a USERS view of the functions.
Set the level of risk for each feature. Use a simple rating scale such as (H, M, L): High,
Medium and Low. These types of levels are understandable to a User. You should be
prepared to discuss why a particular level was chosen.
It should be noted that Section 4 and Section 6 are very similar. The only true difference is the
point of view. Section 4 is a technical type description including version numbers and other
technical information and Section 6 is from the User’s viewpoint. Users do not understand
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 4
technical software terminology; they understand functions and processes as they relate to their
jobs.
7 FEATURES NOT TO BE TESTED
This is a listing of what is NOT to be tested from both the Users viewpoint of what the system
does and a configuration management/version control view. This is not a technical
description of the software, but a USERS view of the functions.
Identify WHY the feature is not to be tested, there can be any number of reasons.
!" Not to be included in this release of the Software.
!" Low risk, has been used before and is considered stable.
!" Will be released but not tested or documented as a functional part of the release of this
version of the software.
Sections 6 and 7 are directly related to Sections 5 and 17. What will and will not be tested are
directly affected by the levels of acceptable risk within the project, and what does not get
tested affects the level of risk of the project.
8 APPROACH (STRATEGY)
This is your overall test strategy for this test plan; it should be appropriate to the level of the
plan (master, acceptance, etc.) and should be in agreement with all higher and lower levels of
plans. Overall rules and processes should be identified.
!" Are any special tools to be used and what are they?
!" Will the tool require special training?
!" What metrics will be collected?
!" Which level is each metric to be collected at?
!"
How is Configuration Management to be handled?
!" How many different configurations will be tested?
!" Hardware
!" Software
!" Combinations of HW, SW and other vendor packages
!" What levels of regression testing will be done and how much at each test level?
!" Will regression testing be based on severity of defects detected?
!" How will elements in the requirements and design that do not make sense or are
untestable be processed?
If this is a master test plan the overall project testing approach and coverage requirements
must also be identified.
Specify if there are special requirements for the testing.
!" Only the full component will be tested.
!" A specified segment of grouping of features/components must be tested together.
Other information that may be useful in setting the approach are:
!" MTBF, Mean Time Between Failures - if this is a valid measurement for the test involved
and if the data is available.
!" SRE, Software Reliability Engineering - if this methodology is in use and if the
information is available.
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 5
How will meetings and other organizational processes be handled?
9 ITEM PASS/FAIL CRITERIA
What are the Completion criteria for this plan? This is a critical aspect of any test plan and
should be appropriate to the level of the plan.
!" At the Unit test level this could be items such as:
!" All test cases completed.
!" A specified percentage of cases completed with a percentage containing some number
of minor defects.
!" Code coverage tool indicates all code covered.
!" At the Master test plan level this could be items such as:
!" All lower level plans completed.
!" A specified number of plans completed without errors and a percentage with minor
defects.
This could be an individual test case level criterion or a unit level plan or it can be general
functional requirements for higher level plans.
What is the number and severity of defects located?
!" Is it possible to compare this to the total number of defects? This may be impossible, as
some defects are never detected.
!" A defect is something that may cause a failure, and may be acceptable to leave in the
application.
!" A failure is the result of a defect as seen by the User, the system crashes, etc.
10 SUSPENSION CRITERIA AND RESUMPTION REQUIREMENTS
Know when to pause in a series of tests.
!" If the number or type of defects reaches a point where the follow on testing has no value,
it makes no sense to continue the test; you are just wasting resources.
Specify what constitutes stoppage for a test or series of tests and what is the acceptable level
of defects that will allow the testing to proceed past the defects.
Testing after a truly fatal error will generate conditions that may be identified as defects but
are in fact ghost errors caused by the earlier defects that were ignored.
11 TEST DELIVERABLES
What is to be delivered as part of this plan?
!" Test plan document.
!" Test cases.
!" Test design specifications.
!" Tools and their outputs.
!" Simulators.
!" Static and dynamic generators.
!" Error logs and execution logs.
!"
Problem reports and corrective actions.
One thing that is not a test deliverable is the software itself that is listed under test items and
is delivered by development.
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 6
12 REMAINING TEST TASKS
If this is a multi-phase process or if the application is to be released in increments there may
be parts of the application that this plan does not address. These areas need to be identified to
avoid any confusion should defects be reported back on those future functions. This will also
allow the users and testers to avoid incomplete functions and prevent waste of resources
chasing non-defects.
If the project is being developed as a multi-party process, this plan may only cover a portion
of the total functions/features. This status needs to be identified so that those other areas have
plans developed for them and to avoid wasting resources tracking defects that do not relate to
this plan.
When a third party is developing the software, this section may contain descriptions of those
test tasks belonging to both the internal groups and the external groups.
13 ENVIRONMENTAL NEEDS
Are there any special requirements for this test plan, such as:
!" Special hardware such as simulators, static generators etc.
!" How will test data be provided. Are there special collection requirements or specific
ranges of data that must be provided?
!" How much testing will be done on each component of a multi-part feature?
!" Special power requirements.
!" Specific versions of other supporting software.
!"
Restricted use of the system during testing.
14 STAFFING AND TRAINING NEEDS
Training on the application/system.
Training for any test tools to be used.
Section 4 and Section 15 also affect this section. What is to be tested and who is responsible
for the testing and training.
15 RESPONSIBILITIES
Who is in charge?
This issue includes all areas of the plan. Here are some examples:
!" Setting risks.
!" Selecting features to be tested and not tested.
!"
Setting overall strategy for this level of plan.
!" Ensuring all required elements are in place for testing.
!" Providing for resolution of scheduling conflicts, especially, if testing is done on the
production system.
!" Who provides the required training?
!" Who makes the critical go/no go decisions for items not covered in the test plans?
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 7
16 SCHEDULE
Should be based on realistic and validated estimates. If the estimates for the development of
the application are inaccurate, the entire project plan will slip and the testing is part of the
overall project plan.
!" As we all know, the first area of a project plan to get cut when it comes to crunch time at
the end of a project is the testing. It usually comes down to the decision, ‘Let’s put
something out even if it does not really work all that well’. And, as we all know, this is
usually the worst possible decision.
How slippage in the schedule will to be handled should also be addressed here.
!" If the users know in advance that a slippage in the development will cause a slippage in
the test and the overall delivery of the system, they just may be a little more tolerant, if
they know its in their interest to get a better tested application.
!" By spelling out the effects here you have a chance to discuss them in advance of their
actual occurrence. You may even get the users to agree to a few defects in advance, if the
schedule slips.
At this point, all relevant milestones should be identified with their relationship to the
development process identified. This will also help in identifying and tracking potential
slippage in the schedule caused by the test process.
It is always best to tie all test dates directly to their related development activity dates. This
prevents the test team from being perceived as the cause of a delay. For example, if system
testing is to begin after delivery of the final build, then system testing begins the day after
delivery. If the delivery is late, system testing starts from the day of delivery, not on a
specific date. This is called dependent or relative dating.
17 PLANNING RISKS AND CONTINGENCIES
What are the overall risks to the project with an emphasis on the testing process?
!" Lack of personnel resources when testing is to begin.
!" Lack of availability of required hardware, software, data or tools.
!" Late delivery of the software, hardware or tools.
!"
Delays in training on the application and/or tools.
!" Changes to the original requirements or designs.
Specify what will be done for various events, for example:
!" Requirements definition will be complete by January 1, 19XX, and, if the requirements
change after that date, the following actions will be taken.
!" The test schedule and development schedule will move out an appropriate number of
days. This rarely occurs, as most projects tend to have fixed delivery dates.
!" The number of test performed will be reduced.
!" The number of acceptable defects will be increased.
!" These two items could lower the overall quality of the delivered product.
!"
Resources will be added to the test team.
!" The test team will work overtime.
!" This could affect team morale.
!" The scope of the plan may be changed.
!" There may be some optimization of resources. This should be avoided, if possible,
for obvious reasons.
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 8
!" You could just QUIT. A rather extreme option to say the least.
Management is usually reluctant to accept scenarios such as the one above even though they
have seen it happen in the past.
The important thing to remember is that, if you do nothing at all, the usual result is that
testing is cut back or omitted completely, neither of which should be an acceptable option.
18 APPROVALS
Who can approve the process as complete and allow the project to proceed to the next level
(depending on the level of the plan)?
At the master test plan level, this may be all involved parties.
When determining the approval process, keep in mind who the audience is.
!"
The audience for a unit test level plan is different than that of an integration, system or
master level plan.
!" The levels and type of knowledge at the various levels will be different as well.
!" Programmers are very technical but may not have a clear understanding of the overall
business process driving the project.
!" Users may have varying levels of business acumen and very little technical skills.
!" Always be wary of users who claim high levels of technical skills and programmers that
claim to fully understand the business process. These types of individuals can cause more
harm than good if they do not have the skills they believe they possess.
19 GLOSSARY
Used to define terms and acronyms used in the document, and testing in general, to eliminate
confusion and promote consistent communications.
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 9
SAMPLE MASTER TEST PLAN
1 TEST PLAN IDENTIFIER RS-MTP01.3
2 REFERENCES
None Identified.
3 INTRODUCTION
This is the Master Test Plan for the Reassigned Sales Re-write project. This plan will
address only those items and elements that are related to the Reassigned Sales
process, both directly and indirectly affected elements will be addressed. The primary
focus of this plan is to ensure that the new Reassigned Sales application provides the
same level of information and detail as the current system while allowing for
improvements and increases in data acquisition and level of details available
(granularity).
The project will have three levels of testing, Unit, System/Integration and Acceptance. The
details for each level are addressed in the approach section and will be further defined in the
level specific plans.
The estimated time line for this project is very aggressive (six (6) months), as such, any
delays in the development process or in the installation and verification of the third party
software could have significant effects on the test plan. The acceptance testing is expected to
take one (1) month from the date of application delivery from system test and is to be done in
parallel with the current application process.
4 TEST ITEMS
The following is a list, by version and release, of the items to be tested:
A. EXTOL EDI package, Version 3.0
If a new release is available prior to roll-out it will not be used until after installation. It will
be a separate upgrade/update project.
B. DNS PC EDI transaction package, Version 2.2
If a new release is available prior to roll-out it will not be used until after installation. It will
be a separate upgrade/update project.
C. Custom PC EDI transaction package (two distributors only).
D. New reassigned sales software, initial version to be Version 1.0
A detailed listing of programs, databases, screens and reports will be provided in the
system and detailed design documents.
E. Order Entry EDI interface software, Current version at time of pilot. Currently,
version 4.1.
F. Reassigned Sales System requirements document, SST_RQMT.WPD version 4.1
G. Reassigned Sales System Design Document, SST_SYSD.WPD version 3.02
H. Reassigned Sales Detail Design Document, SST_DTLD.WPD version 3.04
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 10
5 SOFTWARE RISK ISSUES
There are several parts of the project that are not within the control of the Reassigned Sales
application but have direct impacts on the process and must be checked as well.
A. The local AS/400 based vendor supplied EDI software package. This package will be
providing all the reformatting support from the ANSI X12 EDI formats to the internal
AS/400 data base file formats.
B. The PC based software package installed at each distributor's location (both custom
written and vendor supplied) will be providing the formatting of the distributors data
into the correct EDI X12 formats.
C. Backup and Recovery of the EDI transmission files, local databases and restart of the
translation process, must be carefully checked.
D. The ability to restart the application in the middle of the process is a critical factor to
application reliability. This is especially true in the case of the transmission files as
once the data is pulled from the mail box it is no longer available there and must be
protected locally.
E. Database security and access must be defined and verified, especially for files shared
between the Order Entry application and the Reassigned Sales process. All basic
security will be provided through the AS/400 systems native security process.
6 FEATURES TO BE TESTED
The following is a list of the areas to be focused on during testing of the application.
A. New EDI data acquisition process.
B. Redesigned On-line screens.
C. Redesigned/Converted reports.
D. New Automated Archive process.
E. Interface to the Order Entry system and data bases.
F. Computation of Sales Activity by region for commissions
7 FEATURES NOT TO BE TESTED
The following is a list of the areas that will not be specifically addressed. All testing in these
areas will be indirect as a result of other testing efforts.
A. Non-EDI Order Entry processes.
Only the EDI interface of the Order Entry application will be verified. Changes to the
EDI interface to support Reassigned Sales are not anticipated to have an impact on
the Order Processing application. Order Entry is a separate application sharing the
data interface only, orders will continue to process in the same manner.
B. Network Security and dial-in access.
Changes to include EDI transactions for reassigned sales will have no impact on the security
aspects of the network or the EXTOL/EDI interface.
C. Operational aspects of the EDI process.
Changes to include EDI transactions for reassigned sales will have no impact on the
operational aspects of the EXTOL/EDI interface.
IEEE Test Plan Outline
Foundation Course in Software Testing
Prepared by Systeme Evolutif Limited Page 11
D. PC based spreadsheet analysis applications using Reassigned Sales data.
These applications are completely under the control of the customer and are outside
the scope of this project. The necessary data base format information will be provided
to the customers to allow them to extract data. Testing of their applications is the
responsibility of the application maintainer/developer.
E. Business Analysis functions using Reassigned Sales data.
These applications are completely under the control of the management support team
and are outside the scope of this project. The necessary data base format information
will be provided to the support team to allow them to extract data. Testing of their
applications is the responsibility of the application maintainer/developer.
F. Marketing/Forecasting processes using Reassigned Sales data.
These applications are completely under the control of marketing and are outside the
scope of this project. The necessary data base format information will be provided to
marketing to allow them to extract data. Testing of their applications is the
responsibility of the application maintainer/developer.
8 APPROACH
8.1 Testing Levels
The testing for the Reassigned Sales project will consist of Unit, System/Integration
(combined) and Acceptance test levels. It is hoped that there will be at least one full time
independent test person for system/integration testing. However, with the budget constraints
and time line established; most testing will be done by the test manager with the development
teams participation.
UNIT Testing will be done by the developer and will be approved by the development team
leader. Proof of unit testing (test case list, sample output, data printouts, defect information)
must be provided by the programmer to the team leader before unit testing will be accepted
and passed on to the test person. All unit test information will also be provided to the test
person.
SYSTEM/INTEGRATION Testing will be performed by the test manager and development
team leader with assistance from the individual developers as required. No specific test tools
are available for this project. Programs will enter into System/Integration test after all critical
defects have been corrected. A program may have up to two Major defects as long as they do
not impede testing of the program (I.E. there is a work around for the error).
ACCEPTANCE Testing will be performed by the actual end users with the assistance of the
test manager and development team leader. The acceptance test will be done in parallel with
the existing manual ZIP/FAX process for a period of one month after completion of the
System/Integration test process.
Programs will enter into Acceptance test after all critical and major defects have been
corrected. A program may have one major defect as long as it does not impede testing of the
program (I.E. there is a work around for the error). Prior to final completion of acceptance
testing all open critical and major defects MUST be corrected and verified by the Customer
test representative.
A limited number of distributors will participate in the initial acceptance test process. Once
acceptance test is complete, distributors will be added as their ability to generate the required
EDI data is verified and checked against their FAX/ZIP data. As such, some distributors will
be in actual production and some in parallel testing at the same time. This will require careful
Login to HandyPDF
Tips: Editig or filling the file you need via PC is much more easier!
By logging in, you indicate that you have read and agree our Terms and Privacy Policy.