Login

Fillable Printable Example of a Project WBS

Fillable Printable Example of a Project WBS

Example of a Project WBS

Example of a Project WBS

WBS Example
This is an example of a one way to create a project management Work Breakdown
Structure (WBS).
ElementNumberWBS Element
1OpportunityAssessment Phase
1.01Idea Generation
1.01.01Receive and/or or solicit ideas.
1.01.02Define the OpportunityAssessment Team.
1.01.03Refine the idea through discussions.
1.02Idea Structuring
1.02.01Identify and confirm sponsorship.
1.02.02Document high level description of business need.
1.02.03Identify high-level requirements and critical success factors.
1.02.04Identify primary clients and users.
1.02.05Define high-level business benefits.
1.02.06Identify related projects and affected systems.
1.02.07Identify other stakeholders.
1.02.08Outline scope and schedule for the next phase.
1.02.09Prepare the Project Initiation Document (Project Request section).
1.03Opportunity AssessmentApproval
1.03.01Finalize and submit the Project Request section of Project Initiation Document.
1.03.02Prioritize ideas/business needs based on business-defined criteria.
1.03.03Conduct the Opportunity Assessment Review. Obtain approval to proceed.
1.03.04If approved, enter information into the project database andestablish the potential project in the time
reporting system.
1.03.05If not approved,communicate decision to impacted resources.
1.04Process Closure
1.04.01Assess the OpportunityAssessment Process to capture lessons learned and opportunities for
improvement.
2Initiating Phase
2.01Process Start Up
2.01.01Define/refine Initiating team.
2.01.02Review Project Request information, lessons learned, and Initiating Processes of similar projects.
2.01.03Refine Initiating tasks and create Initiating schedule.
2.01.04Implement time tracking procedures. Establish status reporting.
2.02Project Definition
2.02.01Understand and further define background and current situation, as well as the project objectives.
2.02.02Define/refine project scope and deliverables.
2.02.03Develop and analyze potential options that meet the business need.
2.02.04Select the best alternative and develop a recommended approach.
2.02.05Develop rough order ofmagnitude (ROM) estimate for resources/ costs. Develop a high-level
schedule/timeline for the project.
2.02.06Initiate Business Case development. Focus on business benefits andhigh-level costs in this phase.
2.02.07Identify high-level project risks.
2.02.08Identify project manager and determine appropriate division of responsibilities for remainder of the
project.
2.02.09Plan for next phase. Develop schedule, budget and identify resources for the next phase.
2.02.10Refine Project Request section and complete Project Charter section of the Project Initiation Document.
work-breakdown-structure-example-01.docPage 1 of 5
WBS Example
Element NumberWBS Element
2.03Initiating Approval
2.03.01Finalize and submit the Project Initiation Document, Concept Analysis Document, Business Case, and
other supporting documentation to appropriate manager(s).
2.03.02Prioritize project based on business-defined criteria.
2.03.03Participate in InitiatingApproval Checkpoint Review. Request funding and approval to proceed.
2.03.04If approved, obtain resource and funding commitments to the project from the appropriate authority.
2.03.05If not approved,communicate decision to impacted resources and take appropriate measures to
ensure work is not continued.
2.04Process Closure
2.04.01Assess the Initiating Process to capture lessons learned and opportunities for improvement.
3Planning Phase
3.01Process Start Up
3.01.01Define/refine the Planning team. Review roles and responsibilities.
3.01.02Prepare for and conduct Planning Kick-Off Meeting.
3.01.03Expand and/or update the Planning activities in the existing Project Schedule.
3.02Project Approach
3.02.01Define project measures of success.
3.02.02Refine project scope, objectives, and deliverables.
3.02.03Identify the requirements decision makers and a process for making effective decisions.
3.02.04Gather and document project requirements.
3.02.05Identify, define, and document technology, infrastructure (hardware, desktop, network, etc.), and
support requirements for the project.
3.02.06Refine/validate project approach.
3.02.07Initiate the development of a work breakdown structure (WBS) for organizing project activities.
3.02.08Refine the Business Case based on the additional information developed in the Planning Process
activities.
3.02.09Define the Project Organization, including the Steering Committee, Project Team members, and
Subject Matter Experts. Document in an organization chart.
3.02.10Determine communications requirements and document the communications approach.
3.03Project Schedule/Budget
3.03.01Refine the work breakdown structure (WBS).
3.03.02Identify task sequence and dependencies.
3.03.03Based on project team members’ input, estimate work effort (hours) and duration (time).
3.03.04Identify resource requirements.
3.03.05Create the Project Schedule.
3.03.06Establish the project budget.
3.03.07Review the Project Schedule and Project Budget with the project team, sponsors, and other
appropriate stakeholders.
3.04Project Planning
3.04.01Identify project constraints, dependencies, andassumptions.
3.04.02Identify, analyze, and prioritize project risks.
3.04.03Determine management approaches (e.g., integration, scope, time, cost, quality, human resources,
communications, risk, procurement).
3.04.04Determine change enablementapproach, if applicable, addressing communications, learning, and
rewards.
3.04.05Refine project documentation based on information gathered in the Planning Process.
3.05PlanningApproval
3.05.01Determine the funding source of project monies.
work-breakdown-structure-example-01.docPage 2 of 5
WBS Example
Element NumberWBS Element
3.05.02Prepare Project Fundingdeliverables and review with Controller.
3.05.03Discussthe Project Funding deliverables with senior staff, as appropriate.
3.05.04Prepare for, schedule, and participate in Project Funding Checkpoint (Planning) Review.
3.05.05Revise the Requirements Specification, Project Schedule, Project Budget, and supporting
documentation.
3.05.06If approved, obtain resource and funding commitments from the appropriate authority. Baseline
requirements, schedule,and budget and place all documents in the project repository.
3.05.07If the project is not approved, document the rationale for the decision not to continue and close the
project in the project database.
3.06Process Closure
3.06.01Assess the Planning Process to capture lessons learned and opportunities for improvement.
4Executing/ Controlling
4.01Process Start Up
4.01.01Define/refine the project team. Review roles and responsibilities.
4.01.02Prepare for and conduct the implementation (or phase) kick-off meeting.
4.01.03Review and update the Project Schedule and Project Budget, as required.
4.01.04Begin planning for the implementation of the project solutions. Document strategy and plan.
4.02Integration Management
4.02.01Manage project issues in accordance with the issues management approach defined in the Planning
Process. Issues management includes identifying project issues, assessing the issues’ impacts,
determining and implementing resolutions, and closing issues.
4.02.02Manage change control in accordance with the change management approach defined in the Planning
Process. Change management includes analyzing situations, authorizing change request impact
assessments, assessing requested changes, creating plans to address changes, determining change
actions, and implementing approved changes.
4.02.03Manage project information in accordance with the project information management approach defined
in the Planning Process. Project information management should address file naming conventions,
documentation storage location(s), version control, information owners, and information management
flows.
4.03Scope Management
4.03.01Review deliverable requirements with the team and project stakeholders in accordance with the scope
management approach defined in the Planning Process.
4.03.02Conduct deliverable reviews to validate each deliverable against documented requirements.
4.03.03Complete deliverable review follow-up.
4.04Time Management
4.04.01Collect actual schedule progress in accordancewith the time management approach defined in the
Planning Process.
4.04.02Update the Project Schedule with actual data during the control interval. Generate required reports to
meet the identified needs of the team and supporting organization.
4.04.03Identify and resolve schedule conflicts and resource issues that surface throughout the project.
4.04.04Prepare for and conduct milestone reviews,as appropriate. This review includes reviewing the latest
estimates for completing current activities anddetermining if the project is still on schedule. Prepare a
progress reports and/or executive reports and distribute.
4.05Cost Management
4.05.01Measure and monitor cost progress against the budget and assess variation in accordance with the
cost management approach.
4.05.02Revise cost estimates, as appropriate, and report revisions to appropriate managers.
4.06Quality Management
4.06.01Perform quality assurance in accordance with the quality management approach defined in the
Planning Process. To perform quality assurance, identify quality assurance resources, review quality
planning procedures, review quality control procedures, and define quality improvement plans.
work-breakdown-structure-example-01.docPage 3 of 5
WBS Example
Element NumberWBS Element
4.06.02Conduct quality control reviews in accordance with the quality management approach defined in the
Planning Process.
4.07HR Management
4.07.01Manage the team in accordance with the human resources management approach defined inthe
Planning Process. Team management includes teamadministration, implementing team operating
guidelines, administering team recognition and reward procedures, and coordinating team member
training.
4.07.02Manage business interfaces in accordance withthe human resources management approach defined
in the Planning Process.
4.08Communications Management
4.08.01Review the communications matrix with the project team, as appropriate.
4.08.02Collect project status and progress information in accordance with the communications management
approach defined in the Planning Process.
4.08.03Distribute information in accordance with the Communications Matrix.
4.09Risk Management
4.09.01Identify project risks throughout the project lifecycle.
4.09.02Analyze risks in accordance with the risk management approach defined in the Planning Process.
4.09.03Develop risk responses, as necessary. Responses to consider include acceptance, avoidance,
mitigation, or transference.
4.09.04Respond to actual risk events and update the risk and response log, as required.
4.10Procurement Management
4.10.01Ensure contract terms are fulfilled by reviewing the contents of the contract at several points in the
project. Negotiate andexecute any changes to the contract.
4.10.02Manage the relationship with the contractor, ensuring the contractor(s) are doing what was expected
and satisfying commitments.
4.10.03Close out contracts and perform contractor exit reviews as contracts are completed. If a formal contract
with the vendor exists, conduct a performance review to determine the degree to which the provisions
ofthe contract(s) were met and provide feedback on performance to help improvefuture engagements.
4.11ClientAcceptance
4.11.01Prepare for and conduct Final Deliverable Review(s) and obtain client approval.
4.11.02If approved, continue with the Closing Process.
4.11.03If the review identifies deficiencies, address deficiencies and re-route deliverables for review. If it is
determined that a deficiency will be addressed in a separate project, document that decision to obtain
approval to continue into the Closing Process forthe current project.
4.12Process Closure
4.12.01Assess the Executing/Controlling Process to capture lessons learned andopportunities for
improvement.
5Closing Phase
5.01Project Completion
5.01.01Collect and organize final project schedule and cost information. Update the original and revised
estimates with actual data and update productivity estimates for future use.
5.01.02Archive all project files and media.
5.01.03Close out all logs (e.g., risk, change, issues) to ensure work is complete and issues are closed.
5.01.04Close the project in the time reporting system so that no time will be logged against the project after the
project is complete.
5.01.05Close the project in the project database.
5.01.06Enter appropriate information into best practice, risk, and estimating data knowledge repositories.
5.01.07Begin preparing the Project Closeout Report using information gathered in the Project Completion
activity
5.02Post-Project Review
5.02.01Administer team member questionnaire. Collect and store information in the project repository.
work-breakdown-structure-example-01.docPage 4 of 5
WBS Example
Element NumberWBS Element
Summarize the results of the questionnaire in the Project Closeout Report.
5.02.02Assess client satisfaction. Collect and store information in the project repository. Summarize the results
ofthe questionnaire in the Project Closeout Report.
5.02.03Consolidate lessons learned from previous processes (or phases).
5.02.04Prepare for and conduct a Post-Project Review. Review the draft Project Closeout Report. Review
lessons learned and identify any additional lessons learned. Record any recommended changes to the
process, metrics, tools, techniques, and standards.
5.02.05Follow-up after Post-Project Review, update the Project Closeout Report, and distribute the report to
appropriate team members and stakeholders of the project organization.
5.02.06Enter the project’s lessons learned in the lessons learned knowledge base.
5.03HR Management Closure
5.03.01Conduct final reviews and evaluations of all project staff, acknowledge/recognize team members, and
release project resources in accordance with policies and procedures.
work-breakdown-structure-example-01.docPage 5 of 5
Login to HandyPDF
Tips: Editig or filling the file you need via PC is much more easier!
By logging in, you indicate that you have read and agree our Terms and Privacy Policy.