SAMPLE WORK BREAKDOWN STRUCTURES
VARIOUS TYPES OF PROJECT
Applications Development Project Sample WBS
Management and support
Provide project management
Provide quality control
Conduct meetings and reviews
Materials and supplies
Travel and living costs
Miscellaneous costs
Consulting fees and subcontractor costs
Contingency
Systems development
Requirements specifications
Conduct information-gathering sessions
Prepare logical data model
Prepare logical process model
Physical design
Prepare physical data model
Prepare physical process model
Online system
Prepare detailed design
Program and unit test
Document
Batch system
Prepare detailed design
Batch update facility
Program and unit test
Document
Reporting system
Program and unit test
Document
Integration
Prepare integration plan
System integration and test
Integrate batch update and reporting system
Conduct systems test on batch systems
Integrate batch and online systems
Conduct systems test on complete system
Prepare user documentation
Customer
Conduct milestone reviews
Review and approve deliverables
Conduct user training
Acceptance testing
Page 1
Printed on: September 13, 2016

SAMPLE WORK BREAKDOWN STRUCTURES
VARIOUS TYPES OF PROJECT
Prepare acceptance tests
Conduct acceptance tests
Prepare revisions from acceptance tests
Hand over to customer
Implementation
Prepare implementation plan
Provide support for implementation
Conduct post-implementation review
Page 2
Printed on: September 13, 2016

SAMPLE WORK BREAKDOWN STRUCTURES
VARIOUS TYPES OF PROJECT
IT Facilities Move Project Sample WBS
Management and support
Provide project management
Provide quality control
Conduct meetings and reviews
Materials and supplies
Travel and living
Miscellaneous costs
Consulting fees and subcontractor costs
Contingency
Physical Facilities
Planning
Define move strategy
Prepare interim operations plan
Move plan
Conduct facilities inventory
Conduct applications inventory
Prepare move plan
Facilities move
Site preparation
Prepare site plan
Prepare physical site
Provide environmental and electrical facilities
Provide network connectivity
Set up interim facilities
Conduct move
Cleanup
Clean up original site
Remove interim facilities
Applications move
Transfer applications to interim facilities
Load and test applications
Prepare interim documentation
Monitor operations on interim facilities
Transfer applications to final facilities
Load and test applications
Prepare operations documentation
Commence applications and systems management
Operations
Prepare operations procedures and documentation
Conduct operator training
Prepare help desk procedures and documentation
Customer
Page 3
Printed on: September 13, 2016

SAMPLE WORK BREAKDOWN STRUCTURES
VARIOUS TYPES OF PROJECT
Provide contract management
Conduct milestone reviews
Conduct training
Acceptance testing
Prepare acceptance criteria
Conduct acceptance tests
Hand over to customer
Page 4
Printed on: September 13, 2016

SAMPLE WORK BREAKDOWN STRUCTURES
VARIOUS TYPES OF PROJECT
System Upgrade Project Sample WBS
Management
Provide project management
Provide quality control
Conduct meetings and reviews
Materials and supplies
Travel and living
Miscellaneous costs
Consulting fees and subcontractor costs
Contingency
Acquisition
Hardware acquisition
Prepare specifications
Issue RFPs
Prepare evaluation criteria
Evaluate vendor responses
Conduct demonstrations, site visits, and reference checks
Hardware purchase
Issue purchase orders
Expedite delivery
Software acquisition
Prepare specifications
Issue RFPs
Prepare evaluation criteria
Evaluate vendor responses
Conduct demonstrations, site visits, and reference checks
Software purchase
Issue purchase orders
Expedite delivery
Installation
Hardware installation
Prepare site plan
Provide environmental and electrical facilities
Provide network connectivity
Receive and install hardware
Conduct acceptance tests
Software installation
Receive and install software
Conduct acceptance tests
Application cutover
Planning
Prepare application migration plan
Prepare systems test plan
Page 5
Printed on: September 13, 2016

SAMPLE WORK BREAKDOWN STRUCTURES
VARIOUS TYPES OF PROJECT
Prepare cutover plan
Prepare backout plan
Prepare operations documentation
Cutover
Migrate application
Conduct systems test
Conduct cutover
Commence system and application management
Customer
Provide contract management
Conduct training
Acceptance testing
Prepare acceptance criteria
Conduct acceptance tests
Prepare revisions from acceptance tests
Page 6